22 men can finish a piece of work in 20 days, while 44
women can do the same job in 30 days. How many days will 1 man and 1 woman take to complete the work together?Solution
ATQ,
Let the efficiency of a man and a woman be 'M' and 'W' units/day, respectively.
So, 22 × 20 × M = 44 × 30 × W
Or, M:W = 440 : 1320 = 1 : 3
Let M = 1e and W = 3e
Let the required time be 'T' days
So, (1e + 3e) × T = 22 × 20 × 1e
Or, 4T = 440
∴ T = 440 ÷ 4 = 110 days
- Which of the following numbers is not a perfect square?
A lending library has a fixed charge for the first 7 days and an additional charge for each day thereafter. Sahil paid Rs . 215 for a book kept for 15 ...
- A number exceeds 40 times its reciprocal by 7/8. Determine the number.
Find the greatest 4‑digit number which is exactly divisible by 12, 15 and 20.
In a two digit positive number, the digit in the unit’s place is equal to the square of the digit in ten’s place, and the difference between...
- Find the median of the following observations:
120, 125, 115, 130, 140, 135, 145 - Find the smallest number that is divisible by 14, 28, and 42.
Determine the highest possible value of (x + y) if the number '3x725y4' is divisible by 12.
Find the least number to be added to 1500 to make it a perfect square.
If y = 5, then what is the value of 10y