Question
22 men can finish a piece of work in 20 days, while 44
women can do the same job in 30 days. How many days will 1 man and 1 woman take to complete the work together?Solution
ATQ,
Let the efficiency of a man and a woman be 'M' and 'W' units/day, respectively.
So, 22 × 20 × M = 44 × 30 × W
Or, M:W = 440 : 1320 = 1 : 3
Let M = 1e and W = 3e
Let the required time be 'T' days
So, (1e + 3e) × T = 22 × 20 × 1e
Or, 4T = 440
∴ T = 440 ÷ 4 = 110 days
What is the meaning of ‘Quantum Meruit ’:
Which Section of Indian Evidence Act is not related to “shifting of burden of proof”?
What does the term "transfer of property" mean as per the Transfer of Property Act?
Under the SEBI Act any pooling of funds under any scheme or arrangement, which is not registered with the Board or is not covered under section 11AA (3)...
What is the final section number of the Bhartiya Sakshya Adhiniyam, 2023?
The Ninth Schedule of the Constitution initially shielded laws from Article 14/19/31 challenges. In I.R. Coelho (2007), the Supreme Court held:
Who can decide the language for the arbitral proceedings as per the Arbitration and Conciliation Act?
Sedition means_______________
Which one of the following statements with regard to superintendence of Delhi Special Police Establishment is correct?
The CVC’s jurisdiction explicitly includes: