Question
'P' alone can do a job in 15 days. 'Q' is 60% more efficient than 'P'. 'P' and 'Q' started the work together, but 'P' left after 5 days. Find the time taken by 'Q' to complete the remaining work.
More Time and work Questions
- Ajay started a work and left working after 8 days. Vijay finished the remaining work in next 36 days. Had Ajay left the work after working for 12 days then...
- 5 men and 6 women can do some work in 3 days. If each man is 50% more efficient than a woman, then find the time taken by 9 men to finish the same work tog...
- 36 women can complete a task in 20 days. If 18 women start the task and after 15 days ‘y’ more women join, ensuring the remaining work is completed in anot...
- Pawan and Qureshi can individually complete a certain task in 5 hours and 15 hours, respectively. Pawan begins the task at 9:00 a.m., and they work alterna...
- 'B' is 20% more efficient than 'A.' 'A' began working on a task alone and continued for 8 days, after which 'B' took over and completed the remaining work ...
- A alone can complete 50% of a work in 9 days while B takes 6 days more than A to complete it. If B and C together can complete the work in 12 days, then fi...
- Abhijeet' is 50% less efficient than 'Vivek' and can achieve 25% of the sales target in 8 days.'Chirag' takes 4 days more than 'Vivek' to achieve the targe...
- 'J', 'K' and 'L' can complete a task alone in 42, 21, and 14 days respectively. If 'K' and 'L' work together for 'x' days and leave, then 'J' completes the...
- Anil and Ashish receive Rs.1800 for work of 6 days. If Anil is 3 times efficient than Ashish, then find the daily wage received by Ashish.
- A and B can complete a piece of work in 12 days and 15 days respectively. They start working together, but after 4 days, A leaves. In how many more days wi...