Question
P’s 3 days work is equal to Q’s 5 days work. If P
and Q together can complete the work in 24 days then how much time Q will take to complete 75% of the work?Solution
Ratio of efficiency of P and Q = 5:3 Let the efficiency of P and Q be 5x and 3x units per day respectively. Total work = 8x × 24 = 192x units Required time = (0.75 × 192x)/3x = 48 days
Load factor is often used in marketing dashboards for airlines as a measure of:
A washing Machine Company aggregates prospective customers who are all interested in a low-cost washing machine and respond positively to mail-out marke...
LinkedIn is
Excuses for not making a purchase commitment or decision are called:
A small electronics company manufactures a line of low to moderate quality stereo components that are distributed through wholesalers to mass market ret...
When demand is equal to supply, it is known as _______ demand.
Product modification is common in which stage of the Product Life Cycle?
An owner of two new kittens would most likely use an experiential search or prior experiences when purchasing:
When Rashmi called the toll-free number to order one dozen Roses from Ferns and Petals, she was using:
Which is an example of up-selling?