Question
Two workers, A and B, can finish a task in 36 days and 48
days respectively, working alone. How many days will they take to complete the work together?Solution
ATQ,
Let the total work be 144 units (LCM of 36 and 48)
Efficiency of 'A' = (144 ÷ 36) = 4 units/day
Efficiency of 'B' = (144 ÷ 48) = 3 units/day
Required time = 144 ÷ (4 + 3) = (144 ÷ 7) = 20(4/7) days
Which statement is correct about ” Chandrayaan-3” ?
a. Chandrayaan-3 is a follow-on mission to Chandrayaan-2 to demons...
Pattadakal is a cultural festival of which of the following Indian states?
What is the goal for Gross Enrolment Ratio (GER) in higher education according to NEP 2020?
Which metro station in India holds the title of being the deepest in the country?
Who was awarded the Golden Glove in the ISL 2023-24 season?
Atla Tadde is a traditional festival celebrated in which state of India?
Who is the renowned author of the drama "Vikramorvashi,?
What is the viability gap funding approved per megawatt for the battery storage project in Bihar?
Which company developed an AI-based model called 'MusicLM' capable of generating minutes-long musical pieces from text?
The term Political Party is mentioned in which of the following?