Question
Two workers, A and B, can finish a task in 36 days and 48
days respectively, working alone. How many days will they take to complete the work together?Solution
ATQ,
Let the total work be 144 units (LCM of 36 and 48)
Efficiency of 'A' = (144 ÷ 36) = 4 units/day
Efficiency of 'B' = (144 ÷ 48) = 3 units/day
Required time = 144 ÷ (4 + 3) = (144 ÷ 7) = 20(4/7) days
As per ISA’s World Solar Report, what was the global solar capacity in 2023, showing growth from 1.22 GW in 2000?
What is the proposed financial assistance for Civil Services aspirants from Telangana who qualify for the Mains exams under the Rajiv Gandhi Civils Abha...
Which of the following statements about the cosmic explosion AT2021lwx is NOT true?
Which is the most peaceful country in the world according to the Global Peace Index 2023?
Which river is home to the newly discovered fish species Labeo uru?
To build a data center which the state government has tied up with L&T(Larsen & Toubro) for it?
What is the theme of SEFCO-2025 organized by ?
Which team won the AFC U-23 Asian Cup for the second time by defeating Uzbekistan in the final?
Who is the author of the book “Pride, Prejudice and Punditry”?
What was the growth rate in India's total coking coal imports in Q1FY25 compared to the previous fiscal period? Â