Question
A alone can complete 40% of a work in 18 days while B takes 15 days more than A to complete it. If B and C together can complete the work in 20 days, then find the time taken by C alone to complete the same work.
More Time and work Questions
- A alone can complete 50% of a work in 10 days while B takes 8 days more than A to complete it. If B and C together can complete the work in 12 days, then f...
- Ram can do a piece of work in 12 days and Shyam can do the same work in 20 days. They both started work together, Ram left 4 days before the completion of ...
- A and B can complete a work together in 20 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed by B alone in 3...
- A and B can do a piece of work in 30 days and 40 days, respectively. They began the work together but after a certain time, A leaves off and B completed th...
- 'Arun' alone can complete 60% of the work in 15 days, while 'Arun' and 'Bhaskar' together can complete 80% of the work in 7.5 days. Find the time taken by ...
- Virat can do a piece of work in 30 days and Sachin can do the same work in 45 days. If Virat works for 5 days and got Rs. 2100, and the remaining work will...
- Alex and John can finish a translation project alone in ‘p’ and ‘q’ days, respectively. The time taken by Alex to complete the project is 50% of the time t...
- B needs three times as long as A and C together to finish a job. Also, C needs five times as long as A and B together. If all three working together comple...
- ‘N’ men can complete a work together in 24 days. All of them started the work together, but each day, four men left the work. The total time taken to compl...
- A and B can complete a task together in 24 days, while B alone takes 48 days to finish it. A began working alone and left after ‘x’ days, after which B com...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)