πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      A alone can complete 70% of a work in 21 days while B

      takes 15 days more than A to complete it. If B and C together can complete the work in 20 days, then find the time taken by C alone to complete the same work.
      A 72 days Correct Answer Incorrect Answer
      B 32.5 days Correct Answer Incorrect Answer
      C 30 days Correct Answer Incorrect Answer
      D 36 days Correct Answer Incorrect Answer

      Solution

      Time taken by A alone to complete the entire work = 21/0.7 = 30 days Time taken by B alone to complete the entire work = 30 + 15 = 45 days Let the total work = L.C.M of 30, 45 and 20 = 180 units Then, efficiency of B = (180/45) = 4 units/day Combined efficiency of B and C = (180/20) = 9 units/day So, efficiency of C alone = 9 – 4 = 5 units/day So, time taken by C alone to complete the entire work = (180/5) = 36 days

      Practice Next
      ask-question