Question
A alone can complete 70% of a work in 21 days while B
takes 15 days more than A to complete it. If B and C together can complete the work in 20 days, then find the time taken by C alone to complete the same work.Solution
Time taken by A alone to complete the entire work = 21/0.7 = 30 days Time taken by B alone to complete the entire work = 30 + 15 = 45 days Let the total work = L.C.M of 30, 45 and 20 = 180 units Then, efficiency of B = (180/45) = 4 units/day Combined efficiency of B and C = (180/20) = 9 units/day So, efficiency of C alone = 9 – 4 = 5 units/day So, time taken by C alone to complete the entire work = (180/5) = 36 days
Select the option that represents the letters that when placed from left to right in the blanks below will complete the given letter series.
E G ...
Statements:
All Jasmine are Sunflowers.
Only a few Sunflowers are Tulips.
No Tulip is Rose.
Conclusions:
I. All Jasmi...
In which direction is point D with respect to point H?
Two statements are given below and they are labelled as Assertion (A) and Reason (R).
Assertion (A):
Graphite is used in designing of carb...
In a certain code, VANILLA is written as XXPFNIC. How is CARPENTER written in that code?
Find the odd one out.
Statements: L > M = N > O, O > P ≥ T = R
Conclusion:
I. L > T
II. L ≥ R
Who among the following live immediate below F?
In the question, assuming the given statements to be true, find which of the conclusion (s) among given conclusions is /are definitely true and then giv...
Select the number from among the given options that can replace the question mark (?) in the following series.
317, 324, 333, 354, 477,?