    • Question

      A can finish a job in 15 days and B can finish the same

      job in 20 days. In how many days can they finish it working together?
      A 6 days Correct Answer Incorrect Answer
      B 7.5 days Correct Answer Incorrect Answer
      C 60/7 days Correct Answer Incorrect Answer
      D 10 days Correct Answer Incorrect Answer

      Solution

      ATQ, Let total work = 60 units (LCM of 15 and 20). A’s rate = 60/15 = 4 units/day B’s rate = 60/20 = 3 units/day Together = 4 + 3 = 7 units/day Time = 60 / 7 days