Question
X and Y can complete a piece of work in 20 days. They
worked for 10 days and left. Z completed the rest of the work in 10 days. Find how long Z would take to finish 60% of the same work alone.Solution
ATQ,
Fraction of Work done by X and Y = (10/20) = (1/2)
Fraction of work done by Z = 1 - (1/2) = (1/2)
So, number of days taken by Z alone to complete the entire work = 10 ÷ (1/2) = 20 days
So, time taken by Z to complete 60% of the work = 20 × 0.60 = 12 days
The important unit of a microprocessor is –
During __________ motion of an object along a straight line, the change in velocity of the object for any time interval is zero.
Smog is a combination of –
If input frequency of a full wave rectifier be n, then output frequency would be-
______ is an important metal to form amalgam.
Which Metal is found in the highest proportion in earth’s crust?
Water gets cooled, when ice is immersed in it. It is because of the phenomenon of
In a coil with n turns, what happens to the induced electromotive force (EMF) if the number of turns is doubled while the magnetic flux remains constant?
What is termed as 'mechanical energy' in physics?
The motion of a freely falling body is an example of ______________ accelerated motion.