Question
X and Y can complete a piece of work in 20 days. They
worked for 10 days and left. Z completed the rest of the work in 10 days. Find how long Z would take to finish 60% of the same work alone.Solution
ATQ,
Fraction of Work done by X and Y = (10/20) = (1/2)
Fraction of work done by Z = 1 - (1/2) = (1/2)
So, number of days taken by Z alone to complete the entire work = 10 ÷ (1/2) = 20 days
So, time taken by Z to complete 60% of the work = 20 × 0.60 = 12 days
What is the significance of Section 22 regarding civil courts?Â
Which section stipulates the lawful questions that can be asked in cross examinations?Â
Under Section 140 of the Motor Vehicles Act, the liability to pay compensation for death or permanent disablement is based on which principle?
Whoever intentionally puts any person in fear of any injury to that person, or to any other, and thereby dishonestly induces the person so put in fear t...
If a third person wrongfully deprives the bailee of the use or possession of the goods bailed, or does them any injury, the bailee is entitled to use su...
Which regulatory body in India is responsible for regulating and supervising the capital markets, including stock exchanges, brokers, and other market i...
As per Section 24A of SEBI Act, compounding of offence by Securities Appellate Tribunal can be done
In India sovereignty lies with
Under Section 51(1) of the Consumer Protection Act, 2019, what is the mandatory deposit required from an appellant seeking to appeal a State Commission ...
Which order is related to the maxim action personalis moritur cum personaÂ