Question
βXβ can complete a job in 30 days. βYβ is 50%
more efficient than βXβ. How long will they take to finish 75% of the work together?Solution
Let work = 30x units (since X takes 30 days).
Efficiency of X = 30x / 30 = 1x unit/day.
Y is 50% more efficient, so Y's efficiency = 1x + 0.5x = 1.5x units/day.
75% of work = 30x Γ 0.75 = 22.5x units.
Combined efficiency = 1x + 1.5x = 2.5x units/day.
Time taken = 22.5x / 2.5x = 9 days.
Ajay and Bijay can individually complete a task in 18 days and 24 days, respectively. If they work together to finish the task an...
Find the area enclosed between the curve y = β(25 β xΒ²) and the x-axis in the first quadrant.
Simran goes to a grocery store with some money. She can buy 80 packets of rice or 40 packets of flour with the money with her. However, instead of spend...
A shopkeeper marks a product at 20% above the cost price. He then offers a discount of 15% on the marked price. If he still makes a profit of βΉ200, wh...
The 5th term of a GP is 48 and the 8th term is 384. Find the first term.
6 mangoes are bought for Rs 24 and 3 mangoes are sold for Rs 18. Find the percentage profit or loss.Β
Aman, Bhanu, and Chinu can complete a piece of work individually in 20 days, 30 days, and 60 days, respectively. How many days wi...
In a company with a total of 2250 employees, 32% are permanent employees, while the rest are contractual employees. If 40% of the...
If the numerator of a fraction is increased by 150% and the denominator is increased by ___%, the fraction becomes 4/7. What is the original fraction? W...
"Arjun" can complete a task on his own in 20 days. "Bhuvan" requires 5 days more than "Chirag" to finish the same task, where "Ch...