Question
βXβ can complete a job in 30 days. βYβ is 50%
more efficient than βXβ. How long will they take to finish 75% of the work together?Solution
Let work = 30x units (since X takes 30 days).
Efficiency of X = 30x / 30 = 1x unit/day.
Y is 50% more efficient, so Y's efficiency = 1x + 0.5x = 1.5x units/day.
75% of work = 30x Γ 0.75 = 22.5x units.
Combined efficiency = 1x + 1.5x = 2.5x units/day.
Time taken = 22.5x / 2.5x = 9 days.
An examination of a company's financial records to derive evidence which can be used in a court of law or legal proceeding is known as ________
Find the incorrect option regarding the elasticity of commodities?
Arrange the following ratios in the order in which they appear on a common-size income statement, from top to bottom:
(A) Gross profit margin
...For a manufacturing concern, what will be the effect of increase in debtors on the Cash flow Statement?
A company made credit sales of Rs.72 lakh in the year. If the debtors value at end of the year was Rs.12 lakh, what will be the average age of receivabl...
A portfolio to the right of the market portfolio on the Capital Market Line is:
Post discontinuation of LIBOR, the RBI has proposed to revise the all-in-cost ceiling for ECBs to _______
Commission given on each unit of sales will fall under which of the following cost?
Which of the following is a feature of an incentive and not a reward?
Consider the following statements and state which among the following are the correct statements for Nidhi companies?
A. Nidhi companies can borr...