Question
βXβ can complete a job in 30 days. βYβ is 50%
more efficient than βXβ. How long will they take to finish 75% of the work together?Solution
Let work = 30x units (since X takes 30 days).
Efficiency of X = 30x / 30 = 1x unit/day.
Y is 50% more efficient, so Y's efficiency = 1x + 0.5x = 1.5x units/day.
75% of work = 30x Γ 0.75 = 22.5x units.
Combined efficiency = 1x + 1.5x = 2.5x units/day.
Time taken = 22.5x / 2.5x = 9 days.
What is the role of a CDN (Content Delivery Network) in web development?
Which of the following protocols is used to retrieve emails from a server?
Which of the following is not a type of broadband Internet connection?
Which layer of the OSI model is used for converting data into a format that can be transmitted over a network?
Which network device is used to connect multiple network segments and forward data based on MAC addresses?
Β Which of the following is the type of the computer network?
The βhome pageβ of a web site is _________.
Which of these device is used to provide internet to a network?
Which one of the following is NOT a web browser?
What is the primary purpose of an IP address?