Question
βXβ can complete a job in 30 days. βYβ is 50%
more efficient than βXβ. How long will they take to finish 75% of the work together?Solution
Let work = 30x units (since X takes 30 days).
Efficiency of X = 30x / 30 = 1x unit/day.
Y is 50% more efficient, so Y's efficiency = 1x + 0.5x = 1.5x units/day.
75% of work = 30x Γ 0.75 = 22.5x units.
Combined efficiency = 1x + 1.5x = 2.5x units/day.
Time taken = 22.5x / 2.5x = 9 days.
Source of trypisn enzyme is
Who discovered that the potato spindle tuber disease was caused by small naked ssRNA and called it a viroid?
Poultry industry is one of the largest and fastest growing livestock production systems in the world. The approximate nitrogen content in Poultry manure...
The correct order of crops with respect to their water requirement
The flash point of Biodiesel is:
MPTS stands forΒ
Most suitable crops for dry land are
If there is provision for only one irrigation, then at which stage in wheat the farmer should irrigate the crop?Β
CAS stands for
The net assimilation rate is expressed in terms