Question
A and B together can complete a piece of work in 48 days
while B and C together can complete the same work in 58 days. All of three together can complete 80% of the whole work in 26.4 days then find the time taken by A and C together to complete the whole work. Note: You have to find approx. valueSolution
Time taken by A, B and C together to complete the whole work = 26.4/0.80 = 33 days Let total amount of work = 15312 (LCM of 48, 58 and 33) Efficiency of (A + B) = 15312/48 = 319 units per day Efficiency of (B + C) = 15312/58 = 264 units per day Efficiency of (A + B + C) = 15312/33 = 464 units per day Efficiency of A = 464 – 264 = 200 units per day Efficiency of C = 464 – 319 = 145 units per day Desired time = 15312/345 = 44.4 days = 44 days
Find the radius of the sphere whose volume is 562.5Ï€ cm3
- Length of a chord in a circle of radius 'r' cm, is 14 cm and distance between chord and centre of the circle is 24 cm. Find the value of (4r - 60).
The radius of a circle is 10 cm, and the length of the chord is 12 cm. Find the distance between the chord and the centre of the circle. Â
What will be inradius of an equilateral triangle of side 2 cm?
In a right angle triangle, the product of two sides is half of the square of the third side (i.e., hypotenuse). Accordingly find out the acute angle?
In the given Figure, Find  angle BCD. If AB is a diameter & AB is parallel to CD.
Angles of a triangle are in the ratio 2 : 3 : 7. Find the difference between the largest and smallest angle of the triangle.
If median AD of an equilateral ∆ABC is 6 cm and G is centroid. Find AG?
In ΔABC, PQ is parallel to BC If AP: PB= 3:4 and AQ= 6 cm, AC is equal to?