Question
Ram can do a piece of work in 50 days. He alone worked
at it for 20 days and then Lakshman completed alone the rest work in 30 days. In how many days, they will complete the whole work, working together?Solution
Efficiency of Ram = 100/50 = 2% Work done by Ram in 20 days = 20/50 × 100 = 40% Remaining work = 60% Efficiency of Lakshman = 60/30 = 2% Therefore, required number of days = 100/(2+2) = 100/4 = 25 days
Quick response and efficient consumer response delivery systems are most closely related to:
At a local farmers market, an artisan craftsperson sources supplies for his cabinetry from old wine barrels and wine crates. He communicates to prospect...
According to one of the world's largest publishers, it was unprepared for recent increases in the demand for books about security. To prepare for the sh...
During the days before Diwali, a holiday club wants to get new clients and is coming up with attractive joining offers. What form of non-store retailing...
Which of the following is a special kind of price?
A local micro-brewery uses a nearby stream to power a water-mill to generate electricity to heat their hops and yeast during the beer fermentation proce...
Identifying the prospect's role in the buying center would be typically done at the _____ stage of the personal selling process.
When a person is deprived of basic necessities, such as food, clothing, and shelter, he has unsatisfied __________.
LinkedIn is
SBUs with low growth rate and low relative market share are called _________.