Question

    As per Section 39 of the Contract Act 1872, when a party

    to a contract has refused to perform the contract, in its entirety, what shall be the outcome?
    A Promisee may file a suit in a court of competent jurisdiction. Correct Answer Incorrect Answer
    B Contract is postponed unless stated otherwise. Correct Answer Incorrect Answer
    C Compensation is given for the loss caused. Correct Answer Incorrect Answer
    D The promisee may put an end to the contract. Correct Answer Incorrect Answer

    Solution

    The correct answer is D

    Practice Next