Question
P’s 3 days work is equal to Q’s 4 days work. If P
and Q together can complete the work in 32 days then how much time Q will take to complete 75% of the work?Solution
Ratio of efficiency of P and Q = 4:3 Let the efficiency of P and Q be 4x and 3x units per day respectively. Total work = 7x × 32 = 224x units Required time = (0.75 × 224x)/3x = 56 days
Which river is known as the 'Sorrow of Bihar'.
What initiative did HDFC Bank undertake following its Q4FY24 performance?
Which state has topped the Public Affairs Index 2022?
Which of the following pairs of vitamins and their deficiency diseases is correctly matched?
1) Vitamin C Scurvy
2) Vitamin D Pellagra
...For the second consecutive year, who has become the Chief Minister of the state Tripura?
Sardhana Utsav is organised in which district of Uttar Pradesh?
Which of these famous footballer has announced his retirement from the game on 3rd November, 2022?
Who among the following was nicknamed Lok Nayak?
‘Gatha Swaraj Ki’ was inaugurated as a gallery-cum-exhibition depicting the history of prominent Maratha commanders in ____ state?
 The Ministry of Coal had launched _________ ,a mobile App for reporting unauthorized illegal coal mining.