Question
Three men and 4 women can do a piece of work in 7 days,
whereas 2 men and I woman can do it in 14 days. Seven women will complete the same work in:Solution
M D = M D ⇒ (3 men + 4 women) × 7 = (2 men + 1 women) × 14 ⇒ (3 men + 4 women) = (2 men + 1 women) × 2 ⇒ 3 men + 4 women = 4 men + 2 women ⇒ 2 women = men ⇒ (women ∶ men) = 1 : 2 ⇒ Efficiency Ratio of (women ∶ men) = 1 ∶ 2 ⇒ Total Work = Efficiency × Time ⇒ (3 men + 4 women) × 7 = (2 men + 1 women) × 14 ⇒ (3 × 2 + 4 × 1) × 7 = (2 × 2 + 1 × 1) × 14 = 70 ⇒ Total Work = 70 ⇒ number of days to complete the work by 7 women = Total work/Efficiency ⇒ 70/(7 × 1) ⇒ 10 days
Who has assumed the role of the 26th Director General of the Indian Coast Guard?
With reference to the composition of the Legislative Council in a state of India, which of the following statement/s is/are correct?
I) In the Le...
What is the theme of the World Day Against Child Labour 2024?
What is India’s revised GDP growth projection for the financial year 2024-25, according to the IMF forecast in April 2024?
Which state government recently launched the second edition of the 'Single Window System' (SWS) to facilitate speedy approvals for setting up industries?
Which state’s Nagri Dubraj rice variety has got G.I tag?
What was the purpose of the seven-volume series 'Greatness of Spirit' launched by the Ramon Magsaysay Award Foundation?
Union Minister Dharmendra Pradhan has tied up with whom to empower 'teachers and entrepreneurs'?
The Elphinstone code which introduced a uniform scheme of criminal law was introduced in which year?
Who has been elected as the next President of the European Council?