Question
Three men and 4 women can do a piece of work in 7 days,
whereas 2 men and I woman can do it in 14 days. Seven women will complete the same work in:Solution
M D = M D ⇒ (3 men + 4 women) × 7 = (2 men + 1 women) × 14 ⇒ (3 men + 4 women) = (2 men + 1 women) × 2 ⇒ 3 men + 4 women = 4 men + 2 women ⇒ 2 women = men ⇒ (women ∶ men) = 1 : 2 ⇒ Efficiency Ratio of (women ∶ men) = 1 ∶ 2 ⇒ Total Work = Efficiency × Time ⇒ (3 men + 4 women) × 7 = (2 men + 1 women) × 14 ⇒ (3 × 2 + 4 × 1) × 7 = (2 × 2 + 1 × 1) × 14 = 70 ⇒ Total Work = 70 ⇒ number of days to complete the work by 7 women = Total work/Efficiency ⇒ 70/(7 × 1) ⇒ 10 days
What was the contribution of the livestock sector to the agriculture and allied sector's Gross Value Added (GVA) in the fiscal year 2021-22?
Which of the following statement is incorrect?Â
Micronutrient is essential for the synthesis of Auxin:
Based on mode of organization and functioning groups are classified as:
What is the premium rate payable by PMFBY beneficiaries for Rabi crops (% of SI or Actuarial rate)?
Which of the following is not a base?
National Income means
What was the main objective of the MAHARISHI initiative launched at MACS 2023?
Fusarium wilt disease in gram is mainly caused by
What approximate portion of total rice exports does Non-Basmati White Rice constitute?