Question
Working alone, B can complete the work in 30 days. C is twice as efficient as B and A takes 3 days more than it takes C to complete the work. Working together, in how much time would they be able to complete 7 such works?
More Time and work Questions
- 12 men can complete a work in 10 days, while 10 women can complete the same work in 18 days. In how many days will 4 men and 6 women complete the work toge...
- P alone can finish a piece of work ‘M’ in 5 days while Q takes 3 days to finish it alone. P, Q and R working together can finish the work ‘N’ which is 11 t...
- A, B and C can complete a project individually in 15 days, 20 days and 30 days respectively. They start working together, but C leaves after working for 2 ...
- A alone can complete a piece of work in 15 days, and B alone can complete it in 20 days. They work together, but every third day B does not work. In how ma...
- Ashish and Anil can do a piece of work in 12 days and 16 days respectively. Ashish completed 25% of the work. Find the time taken by Anil to complete the r...
- Alok and Vinay can complete some work alone in 12 days and 20 days respectively. Both of them started the work together but Vinay left the work 4 days befo...
- Rahul, Sameer, and Dinesh can complete a task in 24 days, 36 days, and 18 days, respectively. They started working together, but Rahul left after 3 days. H...
- P alone can finish a piece of work ‘M’ in 8 days while Q takes 4 days to finish it alone. P, Q and R working together can finish the work ‘N’ which is 7 ti...
- A and B working together, can do a piece of work in 4(1/2) hours. B and C working together can do it in 3 hours. C and A working together can do it in 2(1/...
- Ajay and Vijay together can paint a piece of furniture in 11 days. Vijay and Chirag together, as well as Ajay and Chirag together, can paint the same piece...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)