Question
P is 50% more efficient than Q. Q takes 30 days to complete a certain task alone. P and Q started working together and worked for 8 days. After 8 days, R joined them and the three of them together finished the remaining work in 2 days. In how many days can R alone complete the entire task?
More Time and work Questions
- 18 men can finish a work in 15 days by working 8 hours a day. How many more men are needed to finish the work in 12 days by working 6 hours a day?
- A, B, and C together wrap up a task in 14 days. B and C together can finish it in (280/18) days, and C alone completes half in 14 days. Find the ratio of t...
- 25% of the work done by Arjun in 6 days equals 50% of the work done by Karan in 3 days. If Arjun alone finishes the full work in 24 days, find the time Kar...
- P can do a piece of work in 20 days, Q can do the same piece of work in 24 days while R can do it in 30 days. They started working together but after 4 day...
- Riya completes 40% of a task in 24 days, while Siya finishes 30% of the same task in 27 days. Riya begins the task alone and stops after 30 days. How long ...
- Rohit and Mohit began a job together, but after 10 days Rohit left the task. Mohit finished the rest of the job alone in 8 days. Rohit is 40% less efficien...
- P and Q can complete a work in 38 days and 57 days, respectively. P, Q and R together can complete the work in 19 days. If R get a total wage of Rs. 6270 t...
- There are three taps of diameter 2 cm, 3 cm, and 4 cm, respectively. The ratio of the water flowing through them is equal to the ratio of the square of the...
- A can complete a work in 9 days , and B can complete it in 18 days . They work together with C and complete the work in 3 days . In how many days can C...
- 'C' can complete a work in 18 days whereas 'D' can do the same work in 30 days.They started working together but 'C' worked with 60% of his efficiency whil...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)