Question

P is 50% more efficient than Q. Q takes 30 days to complete a certain task alone. P and Q started working together and worked for 8 days. After 8 days, R joined them and the three of them together finished the remaining work in 2 days. In how many days can R alone complete the entire task?

A 10 days
B 12 days
C 15 days
D 18 days
E 20 days