Question
βAβ can do a piece of work in 12 days. βBβ can
do 60% of the same work in 18 days. If they work together for the entire time and get paid Rs.1540, then find the share of βAβ.Solution
Let the total work be 36 units. (LCM of 12 and 18) Efficiency of A = 36/12 = 3 units/day Efficiency of B = (36/18) Γ (60/100) = 6/5 units/day Ratio of the efficiency of A : B = 3 : 6/5 = 15:6 Share of A = (15/21) Γ 1540 = Rs.1100
Polymerase chain reaction (PCR) was invented by:
Which among the following is not a plant derived antioxidant?
Which one the following is Sesame plant response to day length?
People's participation in an extension programme considered significant when
(A) Local leaders participate
(B) Literate section of village...
Which of the following hormone deficiency causes dwarfism in plant?
Chlorine is associated to photosynthesis in production of:
Which pest's larvae, affecting Sorghum crops, cut the growing points and lead to dead-hearts in the plant?
What is the pH range of arid and semi-arid soil?
Income elasticity of inferior goods is ........................?
Mouth parts in thrips belong to the type