πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      7 men and 4 boys can complete a work in 6 days. A man

      completes double the work than a boy. In how many days will 5 men and 4 boys complete the work?
      A 7(3/7) days Correct Answer Incorrect Answer
      B 7(5/7) days Correct Answer Incorrect Answer
      C 6(1/7) days Correct Answer Incorrect Answer
      D 5(2/7) days Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      7 M + 4 B = 6 days and 1 man = 2 boys 7 M + 2 M = 6 days ⇒ 9M = 6 days 1 M = 6 x 9 = 54 days Now, 5 M + 2M = 7M 1 M = 54 days 7M = 54/7 = `7(5/7)` days

      Practice Next
      ask-question