Question
7 men and 4 boys can complete a work in 6 days. A man
completes double the work than a boy. In how many days will 5 men and 4 boys complete the work?Solution
7 M + 4 B = 6 days and 1 man = 2 boys 7 M + 2 M = 6 days ⇒ 9M = 6 days 1 M = 6 x 9 = 54 days Now, 5 M + 2M = 7M 1 M = 54 days 7M = 54/7 = `7(5/7)` days
The four additional Ps of services marketing include each of the following EXCEPT:
At a recent executive meeting, the marketing manager said: "starting tomorrow, we will Tweet five times a day!" This decision is an example of a(n):
If customers perceive a bank as premium due to high pricing alone, the strategy reflects:
Which factor most directly reduces customer acquisition cost?
Profit responsibility, societal responsibility, and stakeholder responsibility are three forms or concepts of:
Which of the following is a psychological factor influencing consumer behaviour?
Value-based pricing is determined mainly by:
A bank analyzes transaction data to predict which customers may close accounts soon. This is an example of:
Which CRM metric indicates percentage of customers leaving bank annually?
Components of a consumer's income include: