Question

A group of 24 men is capable of finishing a task in 15 days. Initially, 12 men begin the job and work on it for 12 days. After this period, an additional 'x' number of men join them, enabling the team to complete the remaining portion of the task in another 12 days. Assuming all men work at the same rate, determine the number 'x' of additional men that joined the work.

A 12
B 8
C 10
D 6
E 4
Practice Next