Question
A group of 24 men is capable of finishing a task in 15
days. Initially, 12 men begin the job and work on it for 12 days. After this period, an additional 'x' number of men join them, enabling the team to complete the remaining portion of the task in another 12 days. Assuming all men work at the same rate, determine the number 'x' of additional men that joined the work.Solution
According to the question, Total work = 24 ├Ч 15 = 360 units Amount of work completed by 12 men in 12 days = 12 ├Ч 12 = 144 units Amount of work to be completed by (12 + x) men = 360 тАУ 144 = 216 units Therefore, (12 + x) ├Ч 12 = 216 Or, 12 + x = 18 Or, x = 6 Hence, option d.
рдирд┐рдореНрди рдореЗрдВ рд╕реЗ рдХреМрди-рд╕рд╛ рд╡рд┐рдХрд▓реНрдк рддрддреНрд╕рдо рддрджреНрднрд╡ рдХреА рджреГрд╖реНрдЯрд┐ рд╕реЗ рд╕рд╣реА рдирд╣я┐╜...
рд╕реВрдЪреА 1┬а рдХреЛ рд╕реВрдЪреА 2┬а рд╕реЗ рд╕реБрдореЗрд▓рд┐рдд рдХреАрдЬрд┐рдП рдФрд░ рд╕реВрдЪрд┐рдпреЛрдВ рдХреЗ рдиреАрдЪреЗ рджрд┐рдП рдЧрдП ...
' рдПрдХрд╛рдПрдХ ' рдореЗрдВ рдХреМрди-рд╕рд╛ рд╕рдорд╛рд╕ рд╣реИ ?
рдирд┐рдореНрдирд▓рд┐рдЦрд┐рдд рдореВрд▓ рдЕрдВрдЧреНрд░реЗрдЬреА рд╡рд╛рдХреНрдп рдФрд░ рдЗрд╕рдХреЗ рд╣рд┐рдиреНрджреА рдореЗрдВ рдЕрдиреВрджрд┐рдд я┐╜...
рдирд┐рдореНрдирд▓рд┐рдЦрд┐рдд рдореЗрдВ рд╕реЗ рдирд┐рдмрджреНрдз рджреБрдХрд╛рдиреЗрдВ рдХрд╛ рдкрд░реНрдпрд╛рдп рд╣реЛрдЧрд╛ ?
' рдЕрдиреНрддрд░реНрдирд┐рд╣рд┐рдд ' рд╢рдмреНрдж рдХрд╛ рд╕рд╣реА рд╕рдВрдзрд┐-рд╡рд┐рдЪреНрдЫреЗрдж рд╣реЛрдЧрд╛
рдЙрддреНрддрдо рдкреБрд░реБрд╖, рдмрд╣реБрд╡рдЪрди, рд╕рдореНрдмрдиреНрдз рдХрд╛рд░рдХ рд╣реИ -
рдпреБрдЧреЛрдВ рдХреА рд╕реВрдЪреА рд╡рд╛рд▓рд╛-
'рдЬрд┐рд╕рдХрд╛ рдирд┐рд╡рд╛рд░рдг рди рд╣реЛ рд╕рдХрддрд╛ рд╣реЛ' рд╡рд╛рдХреНрдпрд╛рдВрд╢ рдХреЗ рд▓рд┐рдП рдПрдХ рд╢рдмреНрдж рд╣реЛрдЧрд╛:
┬ардирд┐рдореНрдирд▓рд┐рдЦрд┐рдд рд╡рд┐рдХрд▓реНрдкреЛрдВ┬а рдореЗрдВ рд╕реЗ┬а рдорд╛рдирджреЗрдп рдХрд╛ рдЕрдВрдЧреНрд░реЗрдЬреА рдкрд░реНрдпрд╛рдп рд╣...