Question
A group of 24 men is capable of finishing a task in 15 days. Initially, 12 men begin the job and work on it for 12 days. After this period, an additional 'x' number of men join them, enabling the team to complete the remaining portion of the task in another 12 days. Assuming all men work at the same rate, determine the number 'x' of additional men that joined the work.
More Time and work Questions
- A and B can do a piece of work in 30 days and 40 days, respectively. They began the work together but after a certain time, A leaves off and B completed th...
- A and B together can finish a job in ‘x’ days, while A alone takes ‘x + 32’ days to complete it. B alone can finish the job in 90 days. If C is 20% more ef...
- P’s 4 days work is equal to Q’s 5 days work. If P and Q together can complete the work in 25 days then how much time Q will take to complete 40% of the wor...
- A and B together, B and C together and A and C together can complete a piece of work in 11 days, 20 days and 12 days respectively. Find the ratio of the ef...
- X can work as fast as Y and Z together. X and Y together can finish the same task 3 times as fast as Z. If all three working together can finish the task i...
- There were 25 workers to complete a job in 10 days. But after 4 days, 10 workers were reassigned. How many more days will be needed now?
- 'A' alone can do some work in 10 days, 'B' alone can do the same work in 15 days. If they work on alternate days, starting with 'B', then the work will be ...
- Lucas, Maya, and Riley can build a wall in 5, 10, and 15 days respectively. If they start the job together and Lucas leaves 3 days before the job is done, ...
- X can do a piece of work in 20 days. He worked at it for 5 days and then Y finished it in 15 days. In how many days can X and Y together finish the work?
- ‘X’ can finish 50% of a job in 8 days. ‘Y’ takes 8 days more than ‘X’ to complete the entire work, and Y is 20% more efficient than ‘Z’. ‘X’ starts the tas...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)