Question
Working together, A and B can do a certain work in 45
days. They work together for 10 days. They complete the remaining work in 28 days with the assistance of C. The work done by C in 3 days is equal to the work done by Bin 2 days. A and C together can complete 70% of the original work inSolution
Let 'a', 'b' and 'c' is the working efficiency of A, B and C respectively. Let the total amount of work required = 90 units The time is taken by A and B to do a certain work = 45 days Therefore, The combined efficiency of A and B 90/ 45 = 2-unit a per day a + b = 2 The amount of work done by A and B in 10 days = 20 units the remaining work = 90-20 = 70 units The amount of work done A and B in the last 28 days [with C] = 56 units The amount of work done by C in 28 days = 70 - 56 = 14 units Therefore, The Efficiency of C =14/28 =1/2 Now, since the work done by C in 3 days is equal to the work done by B in 2 days, The amount of work done by C in 3 days = 3c units The amount of work done by C in 2 days = 2b units So, 3c =2b b =3c/2 =3/2Γ1/2 b=3/4. The efficiency of A =2-3/4 =5/4 Combined efficiency of A and C =1/2 +5/4 =7/4 The 70% of total work =90Γ70/100 =63. Taken time by A =63/ (7/4) = (63Γ4)/7 =252/7 =36days.
‘A’ and ‘B’ together can complete a work in 12 days, while ‘B’ and ‘C’ together can complete the work in...
βMβ and βNβ together can finish a piece of work in 22 days. If βMβ alone can complete it in 55 days, how many days will βNβ alone take?<...
40 men can complete a piece of work in 48 days. βxβ men started the work and after 33 days 64 more men joined them so that whole work was finished i...
Person A can complete a certain task in 20 days, while person B can finish the same task in x days. Together, they can complete the task in 12 days. Det...
The efficiency of A, B, C, D are in the ratio of 6 : 5 : 4 : 3. If A and C can do a work together in 6 days. Then How much days B and D will take to com...
A, B and C together can do a work in p/13 days, A and B together can do the work in p/10 days and B alone can do the work in p/4 days. If C takes 20 day...
Pawan, Bittu, and Raju can individually complete a task in 36 days, 60 days, and 30 days, respectively. They all begin working together, but Raju stops ...
The time taken by P to complete a task is half of the time taken by Q. Q and R working together finish the task in 20 days, while...
A and B together can complete a piece of work in 30 days while A alone can complete 50% of the work in 25 days. Find the time taken by B to compl...
P and Q individually can complete the work in 36 days and 54 days respectively. If the time taken by R alone to complete the work is 1.25 times the time...