Question
Ratio of the work done by P, Q and R in one day is 8:5:9
respectively. They all together can complete the work in 40 days. Q and R worked on it for 32 days. In how many days P will complete the remaining work.Solution
Let total amount work be = 40 x 22 = 880 units Amount of work done by Q and R in 32 days = 32 x 14 = 448 units Amount of work left = 880 – 448 = 432 Required time = 432/8 = 54 days
Answer the questions based on the information given below.
A & B means A is greater than B
A * B means A is not greater than B
A ...
Statements: M % N, N & A, A @ B, B # C
Conclusions: I. C & AÂ Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â II. M # B
...Statements: R > S > T ≥ U; Q ≥ R; W = V < U
Conclusions:
I. S > Q
II. W < T
III. Q > W
In the following question the relationship between different elements is given in the statements followed by three conclusions I, II and III. Read the...
In the question, assuming the given statements to be true, find which of the conclusion (s) among given three conclusions is /are definitely true and ...
Statements:
N < P ≤ I = O; P ≥ J ≥ K ≥ W; Z ≤ M ≤ W
Conclusions:
I) O > Z
II) O = Z
...Statements: M $ K; K & N, N % R, R @ W
Conclusions:Â Â Â Â Â
I. W & KÂ Â Â Â Â Â Â Â
II. K & WÂ Â Â Â Â Â Â Â Â Â Â Â ...
Statements: I ≥ E = S > J < N > V > Q ≤ O
Conclusion
I: I > S
II: Q < N
In the question, assuming the given statements to be true, find which of the conclusion (s) among given two conclusions is /are definitely true and the...
Statements: F > V > W ≥ L > G; F ≤ O = M < I
Conclusions: I. M > LÂ Â Â II. V < I