Question

Ratio of the work done by P, Q and R in one day is 8:5:9 respectively. They all together can complete the work in 40 days. Q and R worked on it for 32 days. In how many days P will complete the remaining work.

A 54 days
B 63 days
C 88 days
D 78 days
E None of these
Practice Next

More Time and work Questions

Hey! Ask a query

🎓
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
  • 200 Questions with Detailed Solutions
  • Section-wise Coverage (GA, English, Quant & Reasoning)