      Question

      A can finish a piece of work in 12 days and B can finish

      it in 18 days. They work together for 4 days, after which B leaves. In how many more days will A complete the remaining work?
      A 9(1/2) days Correct Answer Incorrect Answer
      B 5(1/3) days Correct Answer Incorrect Answer
      C 3(1/2) days Correct Answer Incorrect Answer
      D 7(1/3) days Correct Answer Incorrect Answer

      Solution

      Take total work = LCM of 12 and 18 = 36 units A’s 1-day work = 36 / 12 = 3 units B’s 1-day work = 36 / 18 = 2 units Together 1-day work = 3 + 2 = 5 units Work done in 4 days = 4 Γ— 5 = 20 units Remaining work = 36 βˆ’ 20 = 16 units A alone does 3 units/day. Required days = 16/3 = 5 1/3 days