Question

Puneet and Qureshi together can complete (7/8)th of a piece of work in 9 days, Qureshi and Rohit together can complete (3/5)th of the work in 8 days and Puneet and Rohit together can complete (4/5)th of the work in 9 days. In how many days can Puneet alone do the work?

A 18 days
B 12 days
C 10 days
D 28 days
E None of these
Practice Next