Question
The time taken by P to complete a
task is half of the time taken by Q. Q and R working together finish the task in 20 days, while P and R take 15 days. How long will P and Q together take to complete the task?Solution
ATQ, Let the total work be 60 units. {LCM (20 and 15)} Efficiency of Q + R = 60 ÷ 20 = 3 units/day Efficiency of P + R = 60 ÷ 15 = 4 units/day Let efficiencies be: Q = q, R = r P = 2q (because P works twice as fast) So, (q + r) = 3 ……… (i) (2q + r) = 4 ……… (ii) Subtracting (i) from (ii): q = 1 Efficiency of P = 2 × 1 = 2 units/day Required time = 60 ÷ (1 + 2) = 20 days
Skill India completed how many years in June 2026?
On which date was the MoU between Cochin Shipyard Limited and HD KSOE exchanged during the “Samudra se Samriddhi” event?
The total ABS collection by the National Biodiversity Authority till date has exceeded:
- What is the name of the global cybersecurity company that contributed forensic intelligence to the Digital Threat Report 2024?
Equilibrium price is the price when:
Who received the Rashtriya Tansen Samman during the 2024 Tansen Sangeet Samaroh?
India’s first indigenous multi-stage malaria vaccine is named:
PADMA, the Centralised Pay System for Indian Coast Guard has recently been launched. What does D stand for?
The WAVEX Startup Challenge 2025 aims to develop which multilingual AI solution?
The 16th BRICS Summit 2024, held in Kazan, was chaired by which country?