Question
A can complete 1/4th of a work in 5 days while B can
complete 1/5th of the same work in 6 days. In how many days both of them together can complete the whole work?Solution
To complete the whole work, time taken by
A = 5 X 4 = 20 days
B = 5 X 6 = 30 days
Time taken by both of them together
=> (20 * 30)/(20 + 30) = 12 days
Select the most appropriate option to substitute the Bold segment in the given sentence. If there is no need to substitute it, select 'No substitution'...
- Choose the option which can be substituted for the given words/sentence.
One who believes that the pursuit of pleasure is the most important goal i... Choose the option which can be substituted for the given words/sentence.
A place where wild animals are keptSelect the most appropriate option to substitute the underlined segment in the given sentence. If there is no need to substitute it, select ‘No subst...
Select the option that can be used as a one-word substitute for the given group of words.
An extra copy of handwriting or printing.
Select the most appropriate option that can substitute the bold segment in the given sentence.
When I reached home late, I found my children wa...
Select the word that best expresses the meaning of the underlined word.
A corrupt officer is a disgrace to the whole department. <...
Select the most appropriate option to substitute the bold segment in the given sentence. If there is no need to substitute it, select 'No substitution'...
In each of the following questions, choose the correct alternative which can be substituted for the below given word/ phrase of words.
Deliber...
Select the option that can substitute the highlighted segment in the given proverb correctly. If there is no need to substitute it, select ‘No substit...