      A can complete a work in 40 days. B takes 20 days less

      than A to complete the same work. In how many days can both of them together complete 90% of the work together?
      A 8 days Correct Answer Incorrect Answer
      B 3.6 days Correct Answer Incorrect Answer
      C 5.5 days Correct Answer Incorrect Answer
      D 12 days Correct Answer Incorrect Answer

      Solution

      Time taken by B to complete the work = 40 – 20 = 20 days Let the total work = 40 units Efficiency of A = 40/40 = 1 units/day Efficiency of B = 40/20 = 2 units/day Required time taken = 0.90 x 40/(1+2) = 12 days