Question
A can complete a work in 40 days. B takes 20 days less
than A to complete the same work. In how many days can both of them together complete 90% of the work together?Solution
Time taken by B to complete the work = 40 – 20 = 20 days Let the total work = 40 units Efficiency of A = 40/40 = 1 units/day Efficiency of B = 40/20 = 2 units/day Required time taken = 0.90 x 40/(1+2) = 12 days
Which of the following is not a function of Auxin?Â
Monoembryony is the emergence of one and only one seedling from a seed. The example of monoembryonic variety of citrus is
Evapotranspiration is measured using
White rust of crucifer is caused by:
The fertilizer having all the three primary major nutrients viz. N, P, KÂ is termed as
Citrus canker is _____ disease.
Growing of two or more crops simultaneously intermingled without any specific row pattern is known as:
Which one of the following Law used to explains the proportion of 3:1 obtained at F2?
The Minimum Support Price, MSP for crops is fixed twice a year on the recommendations of
Among the following, where is the International Potato Center is located ?