P and Q can individually complete a piece of work in 30
days and 45 days respectively. If R alone takes 1.5 times the time taken by P and Q together to finish the work, how many days will R take to complete the work?Solution
ATQ,
Time taken by P and Q together to complete the work = (30 × 45)/ (30 + 45) = 18 days
Time taken by R alone to complete the work = 1.5 × 18 = 27 days
Which provision of the Bharatiya Sakshya Adhiniyam governs the admissibility of a dying declaration?
In which of the following cases the constitutional validity of Securities act, 2002 has been tested in accordance with some of the sections of Transfer ...
According to Indian Partnership Act, 1932 the property of the firm includes:
If a bill of exchange is drawn in a set of three,
Under The Indian Contract Act, 1872, requisite for a valid ratification is.
A wishes to prove, by secondary evidence, the contents of a lost document.
Which option DOES NOT pertain to "import" as defined in the SEZ Act?
The maximum number of directors in a public company can be _______________ and it can be more than the said number if the company passes a______________...
What can a company formed under the Companies Act, which has no significant accounting transactions and is intended for a future project or asset holdin...
As per the Code on wages, 2019 the Central Government shall fix floor wage taking into account __________ of a worker in such manner as may be prescribed