Question
'Akshay' alone can do a piece of work in 25 days. 'Ben' alone takes 40 days to do the same work. How much 'Akshay' should be paid out of total wages of Rs. 260, if they worked together for entire duration?
More Time and work Questions
- P, Q, and R can do a project individually in 10, 25, and 20 days. P and Q begin the project, but after 2 days, P is replaced by R. How many more days will ...
- A can complete a work in 20 days. B takes 10 days less than A to complete the same work. In how many days can both of them together complete 90% of the wor...
- ‘A’ and ‘B’ can do a piece of work in 20 days and 25 days, respectively. They started working together but ‘A’ left after 4 days. Find the time taken by ‘B...
- Akhil and Nikhil together can complete a work in 6 days while Nikhil alone takes 18 days to complete 60% of the work. If the efficiency of Sachin is 25% mo...
- Anupam can do a piece of work in 36 days and Rajveer can do it in 15 days. Diksha can do the same work in (17/18) times the number of days required by both...
- A, B and C can complete a piece of work in 12 days, 18 days and 36 days respectively (working alone). They all start working together. After 2 days, C leav...
- A team leader can do a job as fast as three members of the team working together. If one of the member can do the job in 5 hrs, the second one takes 10 hrs...
- Amit and Binod receive Rs.1400 for work of 7 days. If Amit is 4 times efficient than Binod, then find the daily wage received by Binod.
- Two workers, A and B, can finish a task in 36 days and 48 days respectively, working alone. How many days will they take to complete the work together?
- A can complete a work in 12 days and B can complete the same work in 18 days. They work together for 4 days, after which A leaves. In how many more days wi...