πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!


    ⚑ Azaadi sale - Celebrate Independence Day with Flat 55% Off On all courses! 13 to 17 Aug ⚑ Enroll Now

    Question

    40 tailors can stitch a batch of dresses in 30 days. If

    20 tailors started the job and after 15 days β€˜u’ more tailors joined them such that the remaining work got completed in 15 days, then find the value of β€˜u’.
    A 35 Correct Answer Incorrect Answer
    B 37 Correct Answer Incorrect Answer
    C 39 Correct Answer Incorrect Answer
    D 40 Correct Answer Incorrect Answer

    Solution

    Total work = 40 Γ— 30 = 1200 units Work completed by 20 tailors in 15 days = 20 Γ— 15 = 300 units Remaining work = 1200 – 300 = 900 units Let the number of tailors added be β€˜u’. Therefore, (20 + u) Γ— 15 = 900 300 + 15u = 900 15u = 600 u = 40 Number of tailors added = 40

    Practice Next
    ask-question

    Not sure which exam is best for you Talk to our expert

    Get My Free Call