Ganga, Yamuna &Saraswati can complete a piece of work in 30, 40 & 60 days respectively. All 3 of them started working together and after 4 days, Ganga quits. Yamuna left 12 days before the completion of the work. In how many days the work was completed?

A 14 days
B 28 days
C 42 days
D 56 days
E None of these