Ganga, Yamuna &Saraswati can complete a piece of
work in 30, 40 & 60 days respectively. All 3 of them started working together and after 4 days, Ganga quits. Yamuna left 12 days before the completion of the work. In how many days the work was completed?Solution
Let total work = LCM (30, 40 & 60) = 120 units Ganga's 1 day work = 120/30 = 4 units Yamuna's 1 day work = 120/40 = 3 units Saraswati'1 day work = 120/60 = 2 units (Ganga+Yamuna+Saraswati)'s 1 day work = 4+3+2 = 9 units So work done by all in 4 days = 9 `xx` 4 = 36 days, Now Ganga Left. Now for next few days, Yamuna & Saraswati worked together & then Yamuna left 12 days before the completion , it means Saraswati alone works in last 12 days. So Saraswati's work done in 12 days = 12`xx` 2 = 24 So work done in first 4 days & in last 12 days = 36+24 = 60 units Remaining work is done by (Yamuna+ Saraswati) in = 60/(3+2) = 60/5 = 12 days So total days to complete the work = 4+12+12 = 28 days
Solve for x in the equation: 3(x + 2) + 2(2x - 5) = 5x + 9

If x = 19, then the value of x5 - 20x4 + 20x3 - 20x2 + 20x - 1 is
Given a triangle with two sides measuring 12 cm and 16 cm, which of the following cannot be a possible length for the third side?
The mean age of 30 students was calculated as 15 years. However, it was later discovered that one student's age was mistakenly entered as 15 years inste...
In a triangle ABC, a point D lies on AB and points E and F lie on BC such that DF is parallel to AC and DE is parallel to AF. If BE = 4 cm. EF = 6cm. th...
If a = 32, b = c = 31, then find the value of a 3 Β + b 3 Β + c 3 Β β 3abc.
If x3 + y3 = 9 and x + y=3 then the value of x4 + y4 is:
105, 111, 123, 141, ?, 195
Let {x + (1/x)} = 4, then Determine the value of {xΒ² + (1/xΒ²)}