Question
‘A’ can do a piece of work in 10 days. ‘B’ can
do 70% of the same work in 20 days. If they work together for the entire time and get paid Rs.1080, then find the share of ‘A’.Solution
Let the total work be 20 units. (LCM of 10 and 20) Efficiency of A = 20/10 = 2 units/day Efficiency of B = (20/20) × (70/100) = 2/3 units/day Ratio of the efficiency of A : B = 2 : 2/3 = 3:1 Share of A = (3/4) × 1080 = Rs.800
In the question, assuming the given statements to be true, find which of the conclusion (s) among given three conclusions is /are definitely true and t...
In the question, assuming the given statements to be true, find which of the conclusion (s) among given two conclusions is /are definitely true and then...
In the question, assuming the given statements to be true, find which of the conclusion (s) among given two conclusions is /are definitely true and the...
Statements:
A ≥ Z > B ≥ Y; C > B ≥ W
Conclusion:
I. A > W
II. C > Y
Statements:
I @ L © R * A $ M
Conclusions:
I. R * M
II. A % L
III. A % I
Statements: P @ Q, Q # R, R % S
Conclusions: a) P # RÂ Â Â Â Â Â b) P @ S
In the question, assuming the given statements to be true, find which of the conclusion (s) among given three conclusions is /are definitely true and t...
In the question, assuming the given statements to be true, find which of the conclusion (s) among given three conclusions is /are definitely true and ...
Statements:Â Â Â Â Â Â A % B & Z % F; F # C & E; E @ P # D
Conclusions :Â Â Â Â Â I. C @ PÂ Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â II. A % PÂ Â Â Â Â ...
In the following question the relationship between different elements is given in the statements followed by three conclusions I, II and III. Read the...