Question
Ratio of the work done by P, Q and R in one day is 5:4:8
respectively. They all together can complete the work in 40 days. Q and R worked on it for 20 days. In how many days P will complete the remaining work.Solution
Let total amount work be = 40 x 17 = 680 units Amount of work done by Q and R in 20 days = 20 x 12 = 240 units Amount of work left = 680 – 240 = 440 Required time = 440/5 = 88 days
- What does the "H" in the HLOOKUP function of MS Excel stand for?
If a = b in the equation of ellipse x²/a² + y²/b² = 1, then the curve becomes:
The equation of a hyperbola whose conjugate axis equals its transverse axis is:
The average weight of 32 dogs was initially computed to be 45 kg. However, it was later discovered that the weights of two dogs w...
Find the equation if a point P(x, y) is equidistant from A(7, 3) and B(-3, 7).
A car covers the first 40 km of a journey at 60 km/h and the next 60 km at 90 km/h. What is the average speed for the entire journey?
If the speed of a boat in still water is 20 km per hour and the speed of current is 5 km per hour then the time taken by the boat to travel 150 KM with ...
Quantity I: A shopkeeper bought an article for Rs. 3000 and marked its price up by 50%. He then gave two successive discounts of 10% and ‘x’%, makin...
What is the total sales for Product B in all four quarters combined?