Question
Ratio of the work done by P, Q and R in one day is 5:4:8
respectively. They all together can complete the work in 40 days. Q and R worked on it for 20 days. In how many days P will complete the remaining work.Solution
Let total amount work be = 40 x 17 = 680 units Amount of work done by Q and R in 20 days = 20 x 12 = 240 units Amount of work left = 680 – 240 = 440 Required time = 440/5 = 88 days
The Public Distribution System (PDS) is an Indian food security system which evolved as a system for distribution of food grains at affordable prices an...
Who developed The TeacherApp?
The fourth Buddhist Council was convened under the patronage of which ruler?
Recently which of the following institution presented the study on the theme - Alternative Sources of Financing for Municipal Corporations?
On which occasion did Prime Minister Narendra Modi launch the 'Mera Yuva Bharat (MY Bharat)' platform, and what is the key goal of this platform?
The Goods and Services Tax (GST) was implemented in which year?Â
National Mountaineering Day in India is celebrated on:
Where was the first India-Nordic summit held?
What was the primary focus of the Sixth Five Year Plan of India?
In 2021 the National Security Guard (NSG) marks its ______ Raising Day on 16 October.