Question
βMβ is 60% more efficient than βNβ. βNβ
started the work alone and worked for 16 days and after that βNβ is replaced by βMβ. If the total work is completed in 45 days, find the time taken by βMβ to finish the same work alone?Solution
Let the efficiency of βNβ = β5xβ units/day Efficiency of βMβ = β8xβ units/day Time taken by βMβ to complete the remaining work = 45 β 16 = 29 days Total work = 16 Γ 5x + 29 Γ 8x = 312x units Desired time = 312x/8x = 39 days
Who has been appointed as the new MD & CEO of the Canara Bank?
What is the GDP growth projection for India for the fiscal year 2025β26 according to the State Bank of India (SBI)?
Indiaβs first agri chatbot Ama KrushAI launched in Which state?
Which team won the 2024 ICC Men's T20 World Cup title?
Who will launch the report on 'A Green and Sustainable Growth Agenda for the Global Economy'?
According to a FICCI-IBA survey, what is one of the key concerns for Indiaβs banking system?
Who has been appointed as the new Chairman and Managing Director of Bharat Electronics Limited (BEL)?
Which region was categorised as the World’s Most Unequal Region in the World Inequality Report 2022?
What is the central theme of the Vatavaran Film Festival inaugurated in October 2024?
What is the primary objective of the NHAI and IIIT Delhi collaboration?