Question
‘n’ men working 16 hours a day can complete a work in 10 days while (2n – 4) men working 10 hours a day can complete the same work in 9 days. In how many days can (n + 6) men working 12 hours a day complete the same work?
More Time and work Questions
- 35 men can complete a piece of work in 40 days. ‘x’ men started the work and after 30 days 60 more men joined them so that whole work was finished in the d...
- P and Q individually can complete the work in 22 days and 33 days respectively. If the time taken by R alone to complete the work is 1.25 times the time ta...
- A, B, and C together can do a project in (64/7) days. B and C together need (96/9) days, and C alone completes half in 8 days. Find A : B (efficiency).
- ‘A’ and ‘B’ alone can do a certain work in 30 days and 40 days, respectively. Both started the work together but after ‘x’ days ‘A’ left the work and the r...
- 'A' and 'B' alone can complete a work in 10 days and 15 days, respectively. If they worked together and total wage received by them to complete the work is...
- Neil and Oscar together can build a wall in 24 days. Neil takes five times as long as Oscar to build the wall alone. Find the time taken by Oscar to build ...
- ‘P’ can finish a task in 36 days, while ‘Q’ can do the same task in (x + 4) days. If both work together and finish the task in 12 days, what is the value o...
- A alone can complete a piece of work in 15 days, and B alone can complete it in 20 days. They work together, but every third day B does not work. In how ma...
- 'A' alone can do some work in 20 days, 'B' alone can do the same work in 30 days. If they work on alternate days, starting with 'B', then the work will be ...
- A can complete a work in 10 days and B can complete it in 15 days. In how many days will they complete the work together?
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt