Question
span >A and B together can complete a piece of work in 55 days while B and C together can complete the same work in 66 days. All of three together can complete 80% of the whole work in 26.4 days then find the time taken by A and C together to complete the whole work. Note: You have to find approx. value
More Time and work Questions
- A can complete a work in 20 days, B in 30 days and C in 60 days. They work together for 5 days, then C leaves. In how many more days will A and B finish th...
- A can complete a piece of work in 80 days, B takes 20% more time than A to complete the same work while C takes 25% more time than B to complete the whole ...
- ‘X’ and ‘Y’ together can complete a work in 8 days, while ‘Y’ and ‘Z’ together can complete the work in 5 d...
- A task can be done by ‘p’ men in 32 days. If the team had 8 more men, the work would finish in 24 days. Find the value of ‘p’.
- 'A' alone can finish a job in 12 days. If 'A' is twice as efficient as 'B' who is 20% as efficient as 'C', then find the time taken to finish the job if th...
- Numan does 4/ 5 half the work as Gagan in time. If together they take 16 days to complete a piece of work, then how long will Gagan take to complete the wo...
- A alone can complete 70% of a work in 21 days while B takes 15 days more than A to complete it. If B and C together can complete the work in 20 days, then ...
- Karan, Arjun and Krunal alone can complete a work in 50, 75 and 60 days respectively. All of them started working together but after 9 days from start Kara...
- 30 men can complete a piece of work in 11 days. 15 men started the same work and worked for 8 days, and then joined by ‘x’ more men such that the remaining...
- A certain number of students can complete the assignment together in 12 days. All of them started the assignment together, but 20 students left the assignm...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt