Question
span >A and B together can complete a piece of work in 55 days while B and C together can complete the same work in 66 days. All of three together can complete 80% of the whole work in 26.4 days then find the time taken by A and C together to complete the whole work. Note: You have to find approx. value
More Time and work Questions
- A and B together, B and C together and A and C together can complete a piece of work in 12 days, 11 days and 9 days respectively. Find the ratio of the eff...
- A, B and C alone can complete a work in 30, 60 and 45 days respectively. All of them started working together but after 3 days from start A left the job an...
- Suraj is one third as good as workman as Pankaj and together they finish a piece of work in 36 days. The number of days taken by Suraj alone to finish the ...
- Ajay and Vijay can finish a task in 9 days working together. Charu, who is twice as efficient as Vijay, can complete the task alone in 18 days. If Ajay and...
- A’ and ‘B’ together can complete a work in 15 days while ‘A’ takes 20 days to complete the same work alone. If ‘C’ is 50% more efficient than ‘B’, then fin...
- G' can complete (3/4) of a job in 24 days, while 'G' and 'H' together can complete the same job in 16 days. Find the time taken by 'H' to complete 25% of ...
- ‘D’ can type a document in 45 days, but ‘D’ and ‘E’ together can do it in 27 days. If ‘E’ worked for 15 days alone and then left, in how many days will ‘D’...
- A group of workers, all equally efficient, were assigned to complete a job in 16 days. However, 10 workers left the job at the end of each day. Despite thi...
- A can copy 80 pages in 20 hours, A and B together can copy 135 pages in 27 hours. Then Y can copy 20 pages in
- Sachin can do a work in 80 days. He works on it for 10 days and then Saurav alone finishes the remaining work in 42 days. In how many days can Sachin and S...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)