Question
A and C together can paint a wall in 18 days. If C takes
36 days to do it alone, and C works for 27 days after A leaves the job, what is the percentage of work completed by A?Solution
Given: A + C together can paint the wall in 18 days тЗТ Work rate = 1/18 C alone can do it in 36 days тЗТ Work rate = 1/36 C works for 27 days after A leaves Let A and C work together for x days Work by A + C = x ├Ч 1/18 Work by C alone = 27 ├Ч 1/36 = 3/4 Total work = 1 So, x/18 + 3/4 = 1 x/18 = 1 - 3/4 = 1/4 x = 1/4 ├Ч 18 = 4.5 days A's individual rate = 1/18 - 1/36 = 1/36 AтАЩs work in 4.5 days = 4.5 ├Ч 1/36 = 1/8 Hence, A completed 1/8 = 12.5% of the work┬а
рдЖрдкрдХреЗ рдорд┐рддреНрд░реЛ рдореЗрдВ рд╕реЗ рдХреЛрдИ рд╕рдордп┬а рдкрд░ рдирд╣реАрдВ рдкрдВрд╣реБрдЪрд╛ред рд╡рд╛рдХреНрдп рдореЗрдВ┬а рдкрджрдмя┐╜...
рд╡реНрдпрд╛рдпрд╛рдо рд╢рд░реАрд░ рдХреЛ ______рд░рдЦрдиреЗ рдХрд╛ рдПрдХ рдЕрдЪреНрдЫрд╛ рддрд░реАрдХрд╛ рд╣реИрдВ рд╡рд╛рдХреНрдп рдореЗ я┐╜...
рд╡рд┐рд╣рд┐рдд рдХрд╛ рд╡рд┐рд▓реЛрдо рдХреНрдпрд╛ рд╣реЛрдЧрд╛ ?
рдирд┐рдореНрдирд▓рд┐рдЦрд┐рдд рдкреНрд░рд╢реНрди рдореЗрдВ , рдЪрд╛рд░ рд╡рд┐рдХрд▓реНрдкреЛрдВ рдореЗрдВ рд╕реЗ , рдЙрд╕ рд╡рд┐рдХрд▓реНрдк рдХрд╛ я┐╜...
рдЬрд╝рдореАрди рдЖрд╕рдорд╛рди рдПрдХ рдХрд░рдирд╛ ┬ардореБрд╣рд╛рд╡рд░реЗ рдХрд╛ рдЕрд░реНрде рд╣реИрдВ
рдирд┐рдореНрдирд▓рд┐рдЦрд┐рдд рд╡рд┐рдХрд▓реНрдкреЛрдВ┬а рдореЗрдВ рд╕реЗ possession рдХрд╛ рд╣рд┐рдВрджреА рдкрд░реНрдпрд╛рдп рд╣реЛрдЧрд╛я┐╜...
рдХреЗ рд▓рд┐рдП рез/ рдЯреНрдпреВрд╢рди реи/ рдХрд░рдирд╛┬а рей/рдмрд╛рдзреНрдп┬а рек/рдХреЛ рел/рдЪрд╛рд╣рд┐рдП рем/ рдЫрд╛рддреНрд░реЛрдВ рен/ рд╡рд╛...
рд╕рдВрдзрд┐ рдкреВрд░реНрдг рдХрд░реЗрдВ -
рдЬрд▓рдж рдХрд╛ рдЕрд░реНрде ___________ рд╣реИред
рдХрд┐рд╕ рдХреНрд░рдорд╛рдВрдХ рдореЗрдВ ‘ рдХреГрддрд┐ – рдХреГрддреА ’ рд╢рдмреН рдж рдпреБрдЧреН рдо рдХрд╛ рд╕рд╣реА ...
рд░рд╛рдЬрднрд╛рд╖рд╛ рд╕рдорд┐рддрд┐┬а рдХреА рдкреНрд░рдердо рдмреИрдардХ рд╣реБрдИ рдереАред┬а