Question
A and B can complete a task together in 14 days, while B
alone takes 28 days to finish it. A began working alone and left after βxβ days, after which B completed the remaining work in 21 days. Determine the percentage of the total work completed by A.Solution
Let total amount of work be 28 units
Efficiency of (A + B) = 28/14 = 2 units/day
Efficiency of βBβ = 28/28 = 1 unit/day
Amount of work done by βBβ = 21 Γ 1 = 21 units
Percentage of work done by βAβ = {(28 β 21)/28} Γ 100 = 25%
More Time and work Questions
- Which letter and number cluster will replace the question mark (?) to complete the given series?
LT6, KU12, IW24, FZ48, ____ - Which letter-cluster will replace the question mark (?) in the following series?
RGV, UME, ?, AYW, DEF - Which letter-cluster will replace the question mark (?) in the following series?
NPQR, OORQ, PNSP, ____, RLUN - A series is given with one term missing. Choose the correct alternatives from the given ones that will complete the series.
57, 59, 56, 61, 54, ___ - Select the number from among the given options that can replace the question mark (?) in the following series.
17, 18, 22, 31, 47, ___