Question
A and B can complete a task together in 14 days, while B
alone takes 28 days to finish it. A began working alone and left after βxβ days, after which B completed the remaining work in 21 days. Determine the percentage of the total work completed by A.Solution
Let total amount of work be 28 units
Efficiency of (A + B) = 28/14 = 2 units/day
Efficiency of βBβ = 28/28 = 1 unit/day
Amount of work done by βBβ = 21 Γ 1 = 21 units
Percentage of work done by βAβ = {(28 β 21)/28} Γ 100 = 25%
Specific Relief Act is applicable for enforcement of:
What is the enactment date of PFRDA Act?
Which section exempts certain persons from limitation, such as insane persons or those under legal guardianship?Β
How should disputes regarding the status of individuals as whole time officers or employees of an existing insurer be addressed after the appointed day?...
Under Section 63 of the Bharatiya Sakshya Adhiniyam, 2023, which of the following is a NEW requirement compared to Section 65B of the Indian Evidence Ac...
As per the Specific Relief Act when can section 8 of the Act be invoked ___
Consider the following statements about electronic signatures:
1. Electronic signature includes digital signature.
2. Only those electroni...
Which function allows the Board to modify or reject proposals for providing infrastructure facilities in a SEZ?
Res-Judicata is incorporated under which provision of CPC?
Under the PMLA (Prevention of Money Laundering Act), 2002, the "Adjudicating Authority" has the power to provisionally attach property for a period not ...