Question
A and B can complete a task together in 14 days, while B alone takes 28 days to finish it. A began working alone and left after ‘x’ days, after which B completed the remaining work in 21 days. Determine the percentage of the total work completed by
A and B can complete a task together in 14 days, while B alone takes 28 days to finish it. A began working alone and left after ‘x’ days, after which B completed the remaining work in 21 days. Determine the percentage of the total work completed by
A.
More Time and work Questions
- ‘n’ men working 16 hours a day can complete a work in 10 days while (2n – 4) men working 10 hours a day can complete the same work in 9 days. In how many d...
- 'P' and 'Q' together can complete the work in 12 days. 'Q' alone can complete the work in 36 days. If R is 50% more efficient than P, find the time taken b...
- P and Q can complete a piece of work individually in 12 days and 20 days, respectively. They start working together, but after 6 days, Q leaves the work. P...
- A is 20% more efficient than B. How much time will they working together take to complete a job which A alone could have done in 29 days?
- P’s 2 days work is equal to Q’s 5 days work. If P and Q together can complete the work in 30 days then how much time Q will take to complete 60% of the wor...
- ‘A’ can complete a job in 36 days. ‘B’ takes 3 times as long as ‘A’ to finish the same job. If both work together, how much of the work will they finish in...
- 32 workers can complete a task in 18 days. They all started together, but after how many days should 12 workers quit so that the task gets completed in 27 ...
- A, B, and C can individually complete a task in 20 days, 15 days, and 10 days, respectively. B and C begin the task and work together for 3 days, after whi...
- Anand and Manav can collaboratively finish a task in {40/3} days, while Anand alone requires 24 days to complete the same task. Given that Prachi's efficie...
- 'A' alone can do some work in 12 days. 'B' is 50% more efficient than 'A'. 'A' worked alone for 3 days and left. How much time (in days) does 'B' need to f...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)