Question
A and B can complete a task together in 14 days, while B
alone takes 28 days to finish it. A began working alone and left after ‘x’ days, after which B completed the remaining work in 21 days. Determine the percentage of the total work completed by A.Solution
Let total amount of work be 28 units
Efficiency of (A + B) = 28/14 = 2 units/day
Efficiency of ‘B’ = 28/28 = 1 unit/day
Amount of work done by ‘B’ = 21 × 1 = 21 units
Percentage of work done by ‘A’ = {(28 – 21)/28} × 100 = 25%
Aluminium Phosphide is used to control stored grain pest _____
‘Centering’. The first cut on a young tea plant is at which of the following:Â
Water is drawn upwards from the water table in a continuous network of pores. This upward movement of water occurs only in saturated soils is called
What is the major limitation of privatized extension services?
The land-related reform enacted to protect tenants from eviction and secure their right to cultivate the land is known as:
Triazines and triazinones inhibit ______
The critical limit for NO3-N (mg/litre) in drinking water (as per WHO standard is:
Khaira disease of rice can be controlled by spraying of ____________ .
Bengal famine in 1943 was caused due to which disease?
The scientific name of the Italian honey bee is