Question
A and B together can complete a piece of
work in 46 days while B and C together can complete the same work in 52 days. All of three together can complete 80% of the whole work in 26.4 days then find the time taken by A and C together to complete the whole work. Note: You have to find approx. valueSolution
Time taken by A, B and C together to complete the whole work = 26.4/0.80 = 33 days
Let total amount of work = 39468 (LCM of 46, 52 and 33)
Efficiency of (A + B) = 39468/46 = 858 units per day
Efficiency of (B + C) = 39468/52 = 759 units per day
Efficiency of (A + B + C) = 39468/33 = 1196 units per day
Efficiency of A = 1196 – 759 = 437 units per day
Efficiency of C = 1196 – 858 = 338 units per day
Desired time = 39468/775 = 50.9 days = 51 days
More Time and work Questions
230 192 172 ? 122 100
...What value should come in the place of (?) in the following number series?
64, 80, 104, ?, 176, 224
97, 106, ?, 195, 411, 460
What will come in place of the question mark (?) in the following series?
29, 42, ?, 95, 135, 184
Find the missing term:
2, 6, 15, 31, 56, ?
32   48   96   ?   720   2520
82, 98, 130, 178, 242, ?
4 10 ? 62.5 156.25 390.625
...140, 146, 170, 224, ?, 470
7 47 ? 223 359 527
...