Question
span >A and B together can complete a piece of work in 46 days while B and C together can complete the same work in 52 days. All of three together can complete 80% of the whole work in 26.4 days then find the time taken by A and C together to complete the whole work. Note: You have to find approx. value
More Time and work Questions
- Ajay alone can complete a work in 10 days and Bittu alone can complete the same work in 15 days. Ajay starts the work alone and after three days Bittu join...
- Worker P alone can complete a work in 40 days. If workers P and Q together take 25% less time than P alone to complete the same work, then in how many days...
- Carol, Bruce, and Peter can decorate a venue in 7, 14, and 21 days respectively. If they start working together, but Carol leaves 3 days before completion,...
- Anil alone can finish some work in 50 days. Anil and Aman completed the work together and earned Rs. 9,000 as wage. If Aman's wage share is Rs. 3,600, then...
- 'Alex,' 'Ben,' and 'Charlie' can individually complete a task in 40, 60, and 100 days, respectively. They decide to work together, but there's a unique pat...
- Ishita is 0.5 times more efficient than Evita. If both of them work on alternate days starting with Ishita, they can finish the work in 19 days. If Somil a...
- A and B can each finish a task in 32 days and 36 days respectively. They begin the task together, but after 12 days, A leaves. How long will it take for B ...
- Anil and Ashish receive Rs.1500 for work of 5 days. If Anil is 4 times efficient than Ashish, then find the daily wage received by Ashish.
- A work can be completed by ‘A’ and ‘B’, alone in 20 days and 10 days, respectively. Find the number of days taken by ‘C’ to complete the same work alone if...
- It is given that 40% of the work completed by Lokesh is equal to 30% of the work completed by Meena. If Lokesh alone can complete the entire work in 28 day...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)