Question
span >A and B together can complete a piece of work in 46 days while B and C together can complete the same work in 52 days. All of three together can complete 80% of the whole work in 26.4 days then find the time taken by A and C together to complete the whole work. Note: You have to find approx. value
More Time and work Questions
- ‘D’ and ‘E’ together finish a task in 20 days. If ‘D’ is 70% more efficient than ‘E’, how many days will ‘E’ take to complete the task alone?
- A and B can complete a work together in 30 days. If A alone can complete one-third of the work in ‘x’ days and remaining work is completed by B alone in 2x...
- 'Amit' can finish a __ percentage of work in 4 days on his own. 'Bishnu' requires 4 days less than 'Amit' to complete the same task individually. Consequen...
- A, B, C and D are four friends working on a project. The ratio of their efficiencies satisfies C : D = 3 : 4 and A : B = 1 : 2. What is the time taken by D...
- When 24 men work for only 3 days, 5/6th of work remains unfinished. How much work will remain unfinished if 27 men work for only 2 days?
- X, Y, and Z alone can complete a language translation in 60, 90, and 36 days respectively. They started working together, but after 5 days, Z left the job,...
- Tony has 3 sons – Harry, Peter and Murphy. Harry and Peter can complete the work in 24 days and 36 days respectively. In how many days Murphy will complete...
- Ajay, Bjay, and Cheetna can individually finish a task in 20, 24, and 30 days, respectively. They began working together, but Ajay left the task 10 days be...
- 15 men can finish a job in 24 days, while 36 women can do the same job in 20 days. How long will 1 man and 1 woman take to complete the work together?
- 'K' and 'L' together can complete a work in 24 days. They started working together but after 16 days, 'L' left and remaining work was completed by 'K' alon...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)