πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!


    Question

    β€˜A’ is 25% more efficient than β€˜B’. β€˜A’ and

    β€˜B’ work together for 5 days after which β€˜A’ is replaced by β€˜C’. β€˜B’ and β€˜C’ together take 5 more days to finish the work. If β€˜A’ alone could’ve finished the whole work in 16 days, then find the time taken by β€˜C’ to finish 60% work alone.
    A 14 days Correct Answer Incorrect Answer
    B 12 days Correct Answer Incorrect Answer
    C 16 days Correct Answer Incorrect Answer
    D 20 days Correct Answer Incorrect Answer
    E 10 days Correct Answer Incorrect Answer

    Solution

    Let the efficiency of 'B' be 'x' units/day So, efficiency of 'A' = x Γ— 1.25 = '1.25x' units/day Total work = 16 Γ— 1.25x = '20x' units So, work done by 'A' and 'B' together in 5 days = (x + 1.25x) Γ— 5 = '11.25x' units So, remaining work = 20x - 11.25x = '8.75x' units So, efficiency of 'B' and 'C' together = 8.75x Γ· 5 = '1.75x' units per day So, efficiency of 'C' = 1.75x - x = '0.75x' units/day So, required time = (20x Γ— 0.6) Γ· 0.75x = 16 days

    Practice Next
    ask-question