Question
‘A’ is 25% more efficient than ‘B’. ‘A’ and ‘B’ work together for 5 days after which ‘A’ is replaced by ‘C’. ‘B’ and ‘C’ together take 5 more days to finish the work. If ‘A’ alone could’ve finished the whole work in 16 days, then find the time taken by ‘C’ to finish 60% work alone.
Solution
Let the efficiency of 'B' be 'x' units/day So, efficiency of 'A' = x × 1.25 = '1.25x' units/day Total work = 16 × 1.25x = '20x' units So, work done by 'A' and 'B' together in 5 days = (x + 1.25x) × 5 = '11.25x' units So, remaining work = 20x - 11.25x = '8.75x' units So, efficiency of 'B' and 'C' together = 8.75x ÷ 5 = '1.75x' units per day So, efficiency of 'C' = 1.75x - x = '0.75x' units/day So, required time = (20x × 0.6) ÷ 0.75x = 16 days
More Time and work Questions
- 25 men can finish a work in 8 days by working 9 hours a day. How many more men are needed to finish the work in 10 days by working 6 hours a day?
- (x + 8) men working 9 hours a day can complete 60% of a work in 12 days. (x + 2) men working 3 hours a day can complete the remaining work in 32 days. Find...
- A and B together can finish a job in 12 days. B alone takes 30 days. How long will A and C together take to finish the same job if C does one-fourth of A’s...
- A contractor planned to complete a project in 5 days by employing ‘a’ workers. But every day exactly 15 workers were absent. As a result, the work got comp...
- ‘A’ alone can complete a work in 15 days while ‘A’ and ‘B’ together can complete the same work in 10 days. How much percentage of the work, ‘B’ alone can c...
- A can finish a work in 12 days and B can finish the same work in 18 days. They work together for 4 days and then B leaves. In how many more days can A alon...
- ‘A’ and ‘B’ alone can do a certain work in 30 days and 40 days, respectively. Both started the work together but after ‘x’ days ‘A’ left the work and the r...
- Ganga, Yamuna &Saraswati can complete a piece of work in 30, 40 & 60 days respectively. All 3 of them started working together and after 4 days, Ga...
- A 40 hectare field is reaped by 4 men, 6 women and 8 children together in 10 days. If working capabilities of a Man, a Woman and a Child are in the ratio 6...
- Abhay and Bhuvan working together can complete a sales target in 24 days. Bhuvan and Chikku working together can finish the same sales target in 32 days. A...