Question
A can complete a work in 10 days and B can complete the
same work in 15 days. They work together for 2 days and then B alone finishes the remaining work. In how many total days is the work completed?Solution
A’s 1-day work = 1/10 B’s 1-day work = 1/15 Together in 1 day = 1/10 + 1/15 = (3 + 2) / 30 = 5/30 = 1/6 Work done in 2 days together = 2 × 1/6 = 1/3 Remaining work = 1 − 1/3 = 2/3 Now only B works: B’s 1-day work = 1/15 Time to do 2/3 work = (2/3) ÷ (1/15) = (2/3) × 15 = 10 days Total time = 2 + 10 = 12 days
 Choose the combination that completes the sentences.
<...
In the following questions two columns are given. In column-I three sentences are given, each of them consisting of a blank which may or may not be fil...
Column (1)
Match the phrases in Column 1 with the phrases in Column 2.
Two columns are given in each question and each column has three parts of a sentence. Choose the most suitable pair, which makes a grammatically correct...
You are required to match statements from columns 1 and 2 and find which of the following pairs of statement make sense meaningfully and grammatically....
Relevant for Exams: