Question
A job is done by 15 men in 30 days and 30 women in 20
days. How many days will it take for 8 men and 12 women to finish the work?Solution
15 men × 30 days = 450 Women’s 1-day work = 450/(30× 20) = ¾ work (8 Men + 12 Women)’s 1-day work = 8 +12 × ¾ = 17 Days taken by 8 M and 12 women to finish the work = 450/17 days Alternate Method: 15 Men can do this job in 30 days and 30 women can do this job in 20 days It means 45 men or 60 woemn can do this job in = 10 days So 8 Men and 12 women can do this job in = 10/{8/45 + 12/60} = 10/ {8/45+ 1/5} = 10 /{17/45} = 450 /17
Which state government launched the “Namma Canteen” initiative to provide affordable meals?
How many gigawatts of solar module manufacturing capacity has India targeted by 2030?
What percentage of retail inflation was recorded in rural areas of India in November 2024?
According to the CAG, how much shortfall was reported in transferring cess collections to their designated funds?Â
The plant cell wall is primarily made up of ________.Â
Where is the Temple of Hephaestus located?
Who was appointed as the new MD & CEO of IndusInd Bank in August 2025?
- Who won the 2025 ICC Men’s T20 Cricketer of the Year award?
Memorandum of Understanding (MoU) was signed between NIELIT and ITI Egypt to enhance workforce skills, promote employment, address skill gaps, and foste...
Which temple is also known by the name 'Yamanika Tirtha'?