15 men× 30 days = 450 Women’s 1-day work = 450/(30× 20) = ¾ work (8 Men + 12 Women)’s 1-day work = 8 +12× ¾ = 17 Days taken by 8 M and 12 women to finish the work = 450/17 days Alternate Method: 15 Men can do this job in 30 days and 30 women can do this job in 20 days It means 45 men or 60 woemn can do this job in = 10 days So 8 Men and 12 women can do this job in = 10/{8/45 + 12/60} = 10/ {8/45+ 1/5} = 10 /{17/45} = 450 /17
The Atal Pension Yojana (APY) is meant to provide a universal social security system for workers in the unorganized sector. Which of the following group...
Which of the following dams is not situated on the river Betwa?
According to the Forbes List of America’s Richest Self-Made Women, which of these has topped it?
Who is the winner of AFC Women’s Asia Cup 2022?
Azaz Patel is related to which of the following sport?
Which country was the world’s largest recipient in the ‘World Bank’s Remittance Prices Worldwide Database’?
By what instrument or device is relative humidity typically measured?
Which dance form is native to Arunachal Pradesh?
राष्ट्रीय रक्षा अकादमी स्थित है ?
Who assumed the additional role of CEO at the Government e-Marketplace (GeM)?