Question
A job is done by 15 men in 30 days and 30 women in 20
days. How many days will it take for 8 men and 12 women to finish the work?Solution
15 men × 30 days = 450 Women’s 1-day work = 450/(30× 20) = ¾ work (8 Men + 12 Women)’s 1-day work = 8 +12 × ¾ = 17 Days taken by 8 M and 12 women to finish the work = 450/17 days Alternate Method: 15 Men can do this job in 30 days and 30 women can do this job in 20 days It means 45 men or 60 woemn can do this job in = 10 days So 8 Men and 12 women can do this job in = 10/{8/45 + 12/60} = 10/ {8/45+ 1/5} = 10 /{17/45} = 450 /17
Dada Saheb Phalke Award is given for outstanding contribution in the field of
Who are the eligible beneficiaries of Abua Awas Yojna ?
A) Homeless or unattended individuals.
B) Particularly Vulnerable Tribal Group (PV...
In which district of Rajasthan the fair of Sitabari is organised?
What disease in cattle is caused by the bacterium Mycobacterium bovis?
Article 280 of the Constitution is related to which of the following?
What is the upper limit of a single UPI transaction for merchant payments as per NPCI (2024)?
In the list of 100 Most Powerful Women Forbes 2020 the finance minister Nirmala Sitharaman secured the position at?
In ________ Guru Gobind Singh convened a general meeting of the Sikhs ar Anandpur Sahib on Baisakhi day and laid the foundation of Khalsa (or the pure).
What is the full form HAM?
Consider the following statements:
Statement I:
The Government of India mandates the packaging of 100% sugar and food grains in diver...