Question

    'X' can complete 75% of a work in 15 days, whereas 'Y' can

    complete 25% of the same work in 10 days. They both started working together, but 'Y' left the job 'n' days before the work finished. If the entire work is completed in 14 days, then find the value of [0.6n + (n²/5)].
    A 6 Correct Answer Incorrect Answer
    B 1 Correct Answer Incorrect Answer
    C 2 Correct Answer Incorrect Answer
    E None of these Correct Answer Incorrect Answer

    Solution

    ATQ,

    Time taken by 'X' to complete the entire work = (15/75) × 100 = 20 days

    Time taken by 'Y' to complete the entire work = (10/25) × 100 = 40 days

    Let the total work be 40 units (LCM of 20 and 40)

    Efficiency of 'X' = 40/20 = 2 units/day

    Efficiency of 'Y' = 40/40 = 1 unit/day

    ATQ:

    (2 × 14) + [1 × (14 - n)] = 40

    28 + (14 - n) = 40

    42 - n = 40

    n = 2

    Required value = 0.6n + (n²/5) = (0.6 × 2) + {(2 × 2)/5} = 1.2 + 0.8 = 2

    Practice Next

    Relevant for Exams: