    Question

    25% of the work done by Arjun in 6 days equals 50% of

    the work done by Karan in 3 days. If Arjun alone finishes the full work in 24 days, find the time Karan would take to complete the entire work alone.
    A 42 days Correct Answer Incorrect Answer
    B 28 days Correct Answer Incorrect Answer
    C 58 days Correct Answer Incorrect Answer
    D 72 days Correct Answer Incorrect Answer

    Solution

    ATQ,

    Let the efficiency of Arjun and Karan be x units/day and y units/day respectively.

    So,

    0.25 × x × 6 = 0.5 × y × 3

    ⇒ x = (3/1) × y

    Total work = 24 × x = 24x units

    Time taken by Karan = Total work / y = (24x) / y = (24 × 3y) / y = 72 days