Question
Sneha and Meena can complete a project in 24 days and 60 days respectively. Sneha began working first. After how many days should Meena step in so that the project is completed in 20 days?
More Time and work Questions
- P alone can finish a piece of work ‘M’ in 6 days while Q takes 3 days to finish it alone. P, Q and R working together can finish the work ‘N’ which is 6 ti...
- 'R' can independently complete a task in 36 days, whereas 'S' can accomplish 40% of the same work within 16 days. 'S' starts the task solo and withdraws af...
- Akash can finish a task alone in 24 days, while Akash and Bittu working together can complete the same task in 14 days. If Bittu starts the work alone and ...
- P alone can finish a piece of work ‘M’ in 6 days while Q takes 3 days to finish it alone. P, Q and R working together can finish the work ‘N’ which is 12 t...
- A and B together can complete a piece of work in 30 days while A alone can complete 50% of the work in 20 days. Find the time taken by B to complete 70% of...
- Efficiency of A, and B are in the ratio of 2 : 3. If both can do a work together in 60 days. Find out how much days A will take to complete the work alone?
- A alone can finish a piece of work in 10 days and B alone can finish it in 15 days. They work together for 3 days and the remaining work is finished by C i...
- A takes 32 days to complete a work while B can complete the same work in 12 days less than A. If C can complete 25% of the work in 12 days, then find the t...
- A alone can finish the work in 10days and B alone can finish the same work in 15 days. All A, B and C together take 5 days to finish the work. Find the tim...
- P and Q together can complete 75% of a work in 15 days while Q alone takes 40% more time than P and Q together to complete the whole work. Find the time ta...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)