Sneha and Meena can complete a project in 24 days and 60
days respectively. Sneha began working first. After how many days should Meena step in so that the project is completed in 20 days?Solution
ATQ,
Let the total work be 120 units (LCM of 24 and 60)
Efficiency of Sneha = (120 / 24) = 5 units/day
Efficiency of Meena = (120 / 60) = 2 units/day
Let Meena join after 'n' days.
So, 5n + (5 + 2) Γ (20 - n) = 120
β 5n + 140 - 7n = 120
β 2n = 20
β n = 10
When calculating Quick Assets, it is important to exclude certain items from Current Assets to accurately measure a company's liquidity. Quick Assets pr...
Who popularized nudge theory?
Which regulatory body governs Limited Liability Partnership (LLP) firms in India?
Which of the following best describes a Global Depositary Receipt (GDR)?
Given the following information, what is the total of indirect expenses?
What will be the impact on Return on Equity (RoE) if cash is paid to the creditors?
Which of the following activities undertaken by NBFCs is eligible for bank credit, according to the recent Master Circular - Bank Finance to Non-Banking...
Identify the Organisation from the passage given below.
It was created in 1944, as the International Bank for Reconstruction and Development (...
Which of the following are part of Market Infrastructure institutions?
The Central Government has notified the Unified Pension Scheme (UPS) as an option under the National Pension System (NPS) for Central Government employe...