Question
Sneha and Meena can complete a project in 24 days and 60
days respectively. Sneha began working first. After how many days should Meena step in so that the project is completed in 20 days?Solution
ATQ,
Let the total work be 120 units (LCM of 24 and 60)
Efficiency of Sneha = (120 / 24) = 5 units/day
Efficiency of Meena = (120 / 60) = 2 units/day
Let Meena join after 'n' days.
So, 5n + (5 + 2) × (20 - n) = 120
⇒ 5n + 140 - 7n = 120
⇒ 2n = 20
⇒ n = 10
What is the maximum number of rectangles in the given figure?
How many triangles are there in the given figure?
Rekha starts from her house and goes 3 km straight. Then she turns towards her left and goes 1 km. She again turns towards her left and goes 2 km. If sh...
statement:
Residents of this region are frequently faced with incidents of sudden power surges and voltage surges which cause damage to sensitive...
Three statements are given, followed by three conclusions numbered I, II and III.
Assuming the statements to be true, even if they seem to be a...
In this question, three statements are given, followed by three conclusions numbered I, II and III. Assuming the statements to be true, even if they see...
Four pairs of letter-clusters have been given, out of which three are alike in some manner and one is different. Select the one that is different.
In the following question, select the missing number from the given series.
?, 3, 5, 7, 11, 13

Select the option that is related to the third word in the same way as the second word is related to the first word.
Lazy : Hard-working : : Wealthy : ?