Question
Sneha and Meena can complete a project in 24 days and 60 days respectively. Sneha began working first. After how many days should Meena step in so that the project is completed in 20 days?
More Time and work Questions
- ‘M’ and ‘N’ can do a piece of work in 9 days and 18 days, respectively. ‘M’ started working alone and was replaced by ‘N’ after 3 days. In how many days ca...
- A tank can be filled by pipe A in 6 hours and by pipe B in 8 hours. There is also a waste pipe C which can empty the full tank in 12 hours. If all three pi...
- A builder employed 12 workers to complete a job in 18 days. But after 8 days, 4 workers quit. How many more days will be required to complete the remaining...
- "Arnav, Bhanu, and Chinu can finish a task in 18 days, 24 days, and 30 days, respectively. They all begin working together, but Bhanu stops after 4 days, a...
- Efficiency of A and B are in the ratio of 2 : 3. If both can do a work together in 60 days. Find out how much days A will take to complete the work alone?
- Manoj can complete a job in 10 days which Rakesh can do in 15 days. Rakesh can finish a task in 20 days which Suresh can complete in 25 days. In how many d...
- Sonia and Riya decided to complete a piece of work together. Sonia is capable of doing 9 units of work per day, whereas Riya can finish the complete task a...
- ‘A’ and ‘B’ can do a piece of work in 30 days and 20 days, respectively. If they started the work together and worked on it for 4 days, then find the time ...
- P’s 3 days work is equal to Q’s 5 days work. If P and Q together can complete the work in 24 days then how much time Q will take to complete 75% of the wor...
- Eight men and five boys together earn ₹3,240 in 6 days. Meanwhile, three men and two boys working together take 12 days to earn ₹2,484. How many days will ...