Sneha and Meena can complete a project in 24 days and 60
days respectively. Sneha began working first. After how many days should Meena step in so that the project is completed in 20 days?Solution
ATQ,
Let the total work be 120 units (LCM of 24 and 60)
Efficiency of Sneha = (120 / 24) = 5 units/day
Efficiency of Meena = (120 / 60) = 2 units/day
Let Meena join after 'n' days.
So, 5n + (5 + 2) Γ (20 - n) = 120
β 5n + 140 - 7n = 120
β 2n = 20
β n = 10
Araku Valley is located in which of the following state?
Which of the following term/trophies is related with the game of cricket?
Which film won the Best Popular Film Providing Wholesome Entertainment at the 70th National Film Awards?
In case of interstate transactions, the centre would levy & collect the integrated goods and services tax (IGST) under article 269A (I) of the constitu...
Which of the following bodies will manage the βΉ750 crore AgriSURE Fund for start-ups and rural enterprises?
Which of the following statements is/are incorrect about PMKVY?
The Agrarian festival 'Nuakhai' is celebrated in which of the following states?
Indigo airlines has appointed ____ as its Managing Director?
The well known ASER report or Annual Survey of Education Report is published by:
What conditions lead to the formation of Pyrocumulonimbus clouds?