Question
16 men or 24 women can complete a piece of work in 36
days. A man and a woman together complete the work and receive a total wage of Rs. 9,600. Find the difference between the wages received by them.Solution
ATQ, ATQ, Let the efficiency of a man and a woman be 'M' and 'W' units/day respectively. We have, 16M Ă— 36 = 24W Ă— 36 So, 16M = 24W Or, (M/W) = (24/16) = (3/2) Required difference = {(3 - 2) /(3 + 2) } Ă— 9600 = (1/5) Ă— 9600 = Rs.1,920
Karonda is a rich source of
Which soil-forming factor is classified as “passive”?
The World Trade Organization helps in facilitating this trade by providing a framework for negotiating the various trade agreements. Its headquarter is ...
Which fruit is richest source of Riboflavin?
When plant cells are placed in hypertonic solution, they become____
Which is the largest fruit producing district in Bihar?
The juvenile hormone in insects is secreted by which organ?
What is the typical temperature and duration required for UHT sterilization of milk?
Which among the following is categorized as a Mediterranean poultry breed?
Which insect pest exhibits a behavior of moving in an army, destroying fields, and feeding voraciously on all types of vegetation?