Ajay completes half the work done by Rohit in 5/6 of the
time. If they together finish the work in 18 days, how much time will Rohit take to complete the work?Solution
Let time taken by Rohit to complete the work = t days
Ajay takes 2 × (5t/6) = 10t/6 = 5t/3 days.
Efficiency of Rohit = 1/t,
Efficiency of Ajay = 3/5t.
Total efficiency = 1/t + 3/5t = 1/18
Solving for t , we get t = 28.8 days .
Consider the following Statements and choose the option with correct Statements.Â
(I) Pradhan Mantri Jan-Dhan Yojana was launched in 2014.
The Sustainable Development Goals or Global Goals are a collection of seventeen interlinked objectives designed to serve as a shared blueprint for peac...
The government's investment in PM Awas Yojana Urban 2.0, aimed at addressing urban housing needs, includes central assistance of:
The National Pension Scheme (NPS) is a social security initiative by the Central Government. Who among the following are not eligible to become the bene...
What is the primary objective of the National Sickle Cell Anaemia Elimination Program introduced in the Union Budget 2023?
Among the following insect orders, which is exclusively herbivorous in nature?
Which of the following is the prime utility of UMANG App?
Which of the following States does not have any PVTGs?
Who among the following are the beneficiaries of PM FME Schemes?
I- Micro Food Entrepreneurs
II- FPOs
III- SHGs
IV- Co-o...
What is the coverage period for the Pradhan Mantri Jeevan Jyoti Bima Yojana?