      Question

      Ajay completes half the work done by Rohit in 5/6 of the

      time. If they together finish the work in 18 days, how much time will Rohit take to complete the work?
      A 10.5 days Correct Answer Incorrect Answer
      B 28.8 days Correct Answer Incorrect Answer
      C 45.5 days Correct Answer Incorrect Answer
      D None of these Correct Answer Incorrect Answer

      Solution

      Let time taken by Rohit to complete the work = t days

      Ajay takes 2 Γ— (5t/6) = 10t/6 = 5t/3 days.

      Efficiency of Rohit = 1/t,

      Efficiency of Ajay = 3/5t.

      Total efficiency = 1/t + 3/5t = 1/18
      Image
      Solving for t , we get t = 28.8 days .