Question
'Akshay' alone takes 18 days to finish a work while
'Bhim' alone takes 24 days to finish the same work. If 'Akshay' and 'Bhim' work on alternate days starting with 'Akshay', then find the time taken to complete the whole work this way.Solution
Let, the total work be LCM of [18, 24] = 72 units Efficiency of 'Akshay' = (72/18) = 4 units/day Efficiency of 'Bhim' = (72/24) = 3 units/day Amount of work done in first two days = 4 x 1 + 3 x 1 = 7 units Amount of work done in 20 days = 7 x 10 = 70 units Total time taken to complete the work = 2 x (70/7) + (2/4) = 20 + 0.5 = 20.5 days
- If the mean proportion of 3.6 and 1.6 is 'k', then find the value of '5k'.
There are three numbers: A, B, and C. It is given that 45% of A, (3/5) of B, and 1.5 times C are all equal. What is the ratio of A, B, and C?
The ratio of two numbers P and Q is 6: 11 respectively. When 5 is added to P and 84 is subtracted from Q, then the ratio of P and Q becomes 5: 2 respect...
Rs 1080 was divided among Amit, Bhaskar and Charu in the ratio of 13:8:15 respectively. Find the amount received by Amit and Bhaskartogether.
A sum of money is divided among P, Q, R and S in the ratio of 8:9:13:14 respectively. If the share of R's is Rs. 1620 more than the share of Q, then wha...
Ratio of income of Prashant and Palak is 9:8. Income of Chhaya is 4/5 of income of Prashant and difference between income of Palak and Chhaya is ₹2400...
Two years ago the ratio of annual salary of three friends P, Q and R is 4 : 3 : 5. Every year since then the salary of P, Q and R increases by 10%, 12% ...
What is the mean proportion between 3 and 27?
The ratio of the two numbers is 7:13. 150% of the first number is equal to the 60% of the second number. Find the sum of both the numbers.
What is the fourth proportional to 2, 5, 12?