Question
‘P’ and ‘Q’ can complete a project in 45 days and 60 days respectively while ‘P’, ‘Q’ and ‘R’ together can complete the same project in 15 days. Find the time taken by ‘R’ alone to complete 50% of the work.
More Time and work Questions
- An investment at 18% simple interest for 2 years gives Rs. 1,800 as interest. What would be the interest if the same sum is invested at 12% for 4 years?
- Vijay can do a piece of work in 34 days and Sanjay can do the same work in 51 days. If Vijay works for 5 days and got Rs. 1650, and the remaining work will...
- 14 chefs can cook 21 meals in 7 hours. How much time will 10 chefs take to cook 30 meals?
- Calculate the number of days it would take for a team of 8 boys, 5 girls, and 5 children to Construct a building. This building was previously constructed...
- ‘D’ can type a document in 45 days, but ‘D’ and ‘E’ together can do it in 27 days. If ‘E’ worked for 15 days alone and then left, in how many days will ‘D’...
- Three Typists Axe, Wye and Zed working together 3 hours per day and can type 720 pages in 12 days. In a day Wye types as many pages more than Axe as Zed ty...
- 40 laborers were hired to finish a construction job in 50 days. After 35 days of work, only 62.5% of the job was done. How many additional laborers are nee...
- A can complete a work in 12 days, and B can complete the same work in 18 days. How many days will they take to complete the work if they work together?
- 35% of the work done by Sunil in 8 days is equal to 70% of the work done by Raj in 3 days. If Sunil alone can do the work in 24 days, find the number of da...
- ‘M’ is 60% more efficient than ‘N’. ‘N’ started the work alone and worked for 20 days and after that ‘N’ is replaced by ‘M’. If the total work is completed...