Question

‘P’ and ‘Q’ can complete a project in 45 days and 60 days respectively while ‘P’, ‘Q’ and ‘R’ together can complete the same project in 15 days. Find the time taken by ‘R’ alone to complete 50% of the work.

A 12 days
B 18 days
C 10 days
D 22 days
E None of these
Practice Next

More Time and work Questions

Relevant for Exams:

Hey! Ask a query