Question
‘P’ and ‘Q’ can complete a project in 45 days and 60 days respectively while ‘P’, ‘Q’ and ‘R’ together can complete the same project in 15 days. Find the time taken by ‘R’ alone to complete 50% of the work.
More Time and work Questions
- Amit and Chetan can complete a task individually in 30 days and 45 days, respectively. Amit begins the work alone, and after 'd' days, Chetan joins him. To...
- A can complete a piece of work in 10 days , and B can complete the same work in 15 days . They start working together, and after some days A leaves. B co...
- A can fabricate a divider in 23 days , while B alone can assemble it in 26 days, If they construct it together and get an installment of Rs 9800, then find...
- 35 people working 7 hours a day take 22 days to complete a task. How many people working for 6 hours a day are needed to complete five times the given task...
- A can do a work in 45 days and the same the work is done in 15 days by A and B together, then in how many days B can complete the 20% of work?
- P and Q can individually complete a piece of work in 30 days and 45 days respectively. If R alone takes 1.5 times the time taken by P and Q together to fin...
- Atul, Qureshi, and Chintu can individually complete a certain task in 27 days, 30 days, and 36 days, respectively. They all begin working on the task toget...
- A and B together can complete a work in 10 days. B and C together can do it in 12 days, and A and C together can do it in 15 days. In how many days will al...
- A can do a piece of work in 21 days and B in 28 days. If they together work on it for 5 days, then the fraction of the work that is left is :
- Machine X is 100% more efficient than Machine Y, and Machine Y is 75% more efficient than Machine Z. Machines X and Z, working together, can complete a cer...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)