Question
Nakul can do a piece of work in 12 days; Aaravya is 50%
more efficient than Nakul. How much more time does Nakul take than Aaravya to do the same piece of work?Solution
Nakul can do a piece of work = 12 days. Let the efficiency of Nakul =100 So, Aaravya’s efficiency =150. [Nakul][Aaravya] 100150 2:3Efficiency 3:2time. ATQ- 3=12 1=4 Aaravya’s time =2×4=8. Maximum time =12-8 =4days.
“Ek Ped Maa k Naam” campaign was launched on the World Environment Day celebrated on:
What is the standard time frame for supplying information to an applicant under the RTI Act 2005?
What is the primary objective of the Smart Cities Mission in India?
Which of the following is a potential benefit of the Health Facility Registry under the ABDM?
The major aim of the PM Away Yojna Gramin is to provide a pucca house with basic amenities to all rural families, who are homeless or living in kutcha o...
Consider the following Statements about Samagra Shiksha Abhiyan and choose the option with correct Statements.
(1) Samagra Shiksha Abhiyan was...
Identify the purpose of Shram Suvidha Portal
What is the primary objective of the National Gopal Ratna Award?
Government fixes Minimum Support Price (MSP) for 22 mandated agricultural crops and Fair & Remunerative Price (FRP) for:
Which of the following are the components of AASHA?
1. Price Support Scheme (PSS),
2. Pri...