(A+B+C)C 2842 84 32 The efficiency of A+B+C =3 Efficiency of C =2 Efficiency of (A+B) =A+B+C -C=3-2=1 A and B work both together =84/1 = 84 days.
A and B can do a piece of work in 12 days and 18 days, respectively. They start working together, and after 4 days, A leaves the work. How many more day...
Working alone, ‘X’ and ‘Y’ can complete a work in 16 days and 10 days, respectively. They started working together but af...
30 men can complete a piece of work in 11 days. 15 men started the same work and worked for 8 days, and then joined by ‘x’ more men such that the re...
A and B together can complete a piece of work in 12 days, while B and C together can complete the same work in 15 days. A and C together can complete th...
John does ½ piece of work in 3 hours, Joe does ¼ of the remaining work in 1 hour and George finishes remaining work in 5 hours. How long w...